What are the 5 main stages of DB Leadership? - ANSWER-1. Project
team formation and alignment.
2. Project pursuit and procurement.
3. Design integration and advancement.
4. Construction.
5. Closeout and Commissioning.
_____ must manage the entire process - ANSWER-Design-Builders
What does IDWP stand for? - ANSWER-Integrated Design Work Plan
Which phase commitments sets the stage for Integrated Project
Leadership and Design-Build Process Control? - ANSWER-Proposal
Phase Commitments
The Construction process is _____ while the design process is ______. -
ANSWER-- sequential
- iterative
_____ problem solving is what creates the opportunity to optimize the
project. - ANSWER-Integrated
Create and _____ a culture for success - ANSWER-Sustain
,DBIA EXAM 2 LATEST 2023-2024 ACTUAL EXAM 200
QUESTIONS AND CORRECT DETAILED ANSWERS
WITH RATIONALES (VERIFIED ANSWERS) |ALREADY
GRADED A+
_____ _____ _______ create a shared vision of project success. -
ANSWER-Team Alignment Sessions
Commitment to Project goals promotes team _____ and _____. -
ANSWER-- integration
- cohesion
Proximity leads to _____ -- the power of overhearing. - ANSWER-
communication
Communication leads to __________ -- promotes common knowledge. -
ANSWER-understanding
Understanding leads to _____ -- interdisciplinary fluency develops One
Team. - ANSWER-respect
_____ fosters cohesion -- one team acts as one team - ANSWER-
Respect
Joint execution planning drives early _____-_____. - ANSWER-
decision-making
, DBIA EXAM 2 LATEST 2023-2024 ACTUAL EXAM 200
QUESTIONS AND CORRECT DETAILED ANSWERS
WITH RATIONALES (VERIFIED ANSWERS) |ALREADY
GRADED A+
What are the 4 DB Team Integration roles? - ANSWER-1. Integrated
Project Leader (DB - PM).
2. Designer of Record (A/E).
3. Design Manager.
4. Estimator (A/E).
Who leads the project team and manages team dynamics?
a) Integrated Project Leader
b) Designer of Record
c) Design Manager
d) Estimator - ANSWER-a) Integrated Project Leader
Who balances the Owner's needs plus design and construction?
a) Integrated Project Leader
b) Designer of Record
c) Design Manager
d) Estimator - ANSWER-a) Integrated Project Leader
Who is licensed to protect the health, safety and welfare of the public?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller erickarimi. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $25.99. You're not tied to anything after your purchase.