Clb023 Software Cost Estimating 1) Which of the following is NOT an example of a consideration for the Interfaces and Dependencies component of a software estimating plan? [Evaluate the appropriateness and completeness of the estimating plan for a software estimate] [Remediation Accessed :N] The co...
clb 023 defense acquisition university clb023 software cost estimating test fall 2023
Written for
National Defense University
Clb023 Software Cost Estimating
All documents for this subject (2)
Seller
Follow
darrelmay002
Reviews received
Content preview
Clb023 Software Cost Estimating
1) Which of the following is NOT an example of a consideration for the Interfaces
and Dependencies component of a software estimating plan? [Evaluate the
appropriateness and completeness of the estimating plan for a software estimate]
[Remediation Accessed :N]
The command and control (C2) system being estimated must communicate with
an existing Identification Friend or Foe (IFF) system
The estimate for a major Tier 2 subcontractor must include both hardware and
software development
Contractor engineers supporting operational test and evaluation (OT&E) will be
included as part of the contractor estimate, but the government personnel
conducting the tests much be included in the government staffing estimate
The independent verification and validation (IV&V) of software is conducted
under a separate contract and will be estimated as a separate cost element
2) True or False: If warranted, “risk dollars” may be a part of certain elements of the
Program Work Breakdown Structure (PWBS). [Appraise the adequacy of the cost element
structure (CES) for a software estimate]
Fals
e
True
3) Which of the following assumptions would NOT be needed when estimating
software development effort? [Develop a set of ground rules and assumptions (GR&A) for a
software estimate] [Remediation Accessed :N]
The base year for estimation
dollars
The time available for the
development
The degree of code
reuse
The level of proficiency of the software
developer
4) Which of the following is NOT typically captured by a Software Resources Data
Report (SRDR)? [Compare various sources of software data] [Remediation Accessed :N]
Labor categories and labor
,Clb023 Software Cost Estimating
rates
Software
size
Development
schedule
Labor resources for software
development
Software
quality
5) Data points to support parametric software estimates model should be analyzed to
ensure they are [Recommend appropriate data normalization steps to support software cost
estimates] [Remediation Accessed :N]
homogeneous and comparable to the new system’s
parameters
heterogeneous and comparable to the new system’s
parameters
homogeneous and significantly above the maximum of the new system’s
parameters
heterogeneous and significantly below the minimum of the new system’s
parameters
6) Which of the following is least likely to have an impact on a SLOC/hr productivity
metric? [Critique productivity as a commonly-cited software metric] [Remediation
Accessed :N]
Hours per standard labor
month
Experience level of the development
staff
Programming language
used
Complexity of software being
developed
7) Which of the following is NOT a generally-accepted software sizing method? [Relate
the primary software cost drivers to each other and to development cost] [Remediation
Accessed :N]
, Clb023 Software Cost Estimating
Language
Points
Source Lines of Code
(SLOC)
Function
Points
Object
Points
Story
Points
8) Which of the following are NOT generally well-estimated via traditional SLOC-based
methods for custom-developed software? [Evaluate the use of parametric, analogy, and other
techniques in software cost estimating]
COTS software integration, database development, and ERP system
implementation
COTS software integration
only
Database development
only
ERP system implementation
only
COTS software integration and ERP system
implementation only
9) Parametric estimating is a process consisting of these steps: [Summarize the use of
cost estimating relationships (CERs) and schedule estimating relationships (SERs) in software
estimating]
collect data; identify cost drivers; develop cost estimating relationships; build a
parametric model
build a parametric model; collect data; identify cost drivers; develop cost
estimating relationships
collect data; perform a comparative analysis; apply
cost factors
collect data; perform a comparative analysis; apply
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller darrelmay002. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $7.99. You're not tied to anything after your purchase.