100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION) $11.49   Add to cart

Exam (elaborations)

TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION)

1 review
 439 views  17 purchases

TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION) QUESTION 1 An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks. Correct Answer: A QUESTION 2 Which document describes the necessary i...

[Show more]

Preview 4 out of 234  pages

  • November 11, 2022
  • 234
  • 2022/2023
  • Exam (elaborations)
  • Questions & answers
All documents for this subject (4)

1  review

review-writer-avatar

By: yibeltalabate • 1 year ago

reply-writer-avatar

By: smartgrades • 1 year ago

Thank you @yibeltalabate. Success in your studies

avatar-seller
smartgrades
TEST BANK FOR PMI (PMP) EXAM 6TH EDITION PMBOK (COMPLETE SOLUTION) QUESTION 1 An element of the project scope statement is: A. Acceptance criteria. B. A stakeholder list. C. A summary budget, D. High-level risks. Correct Answer: A QUESTION 2 Which document describes the necessary information to determine if a project is worth the required investment? A. Cost baseline B. Service level agreement C. Memorandum of understanding D. Business case Correct Answer: D QUESTION 3 Which input to the Plan Risk Management process provides information on high-level risks? A. Project charter B. Enterprise environmental factors C. Stakeholder register D. Organizational process assets Correct Answer: A QUESTION 4 Which item is an example of personnel assessment? A. Resource calendar B. Tight matrix C. Team -building activity D. Focus group Correct Answer: D QUESTION 5 Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project? A. Feedback analysis B. Stakeholder analysis C. Communication management plan D. Stakeholder management plan Correct Answer: D QUESTION 6 Which input to the Identify Stakeholders process provides information about internal or external parties related to the project? A. Procurement documents B. Communications plan C. Project charter D. Stakeholder register Correct Answer: C QUESTION 7 The Identify Stakeholders process is found in which Process Group? A. Initiating B. Monitoring and Controlling C. Planning D. Executing Correct Answer: A QUESTION 8 An input to Develop Project Charter is a/an: A. Business case. B. Activity list. C. Project management plan. D. Cost forecast. Correct Answer: A QUESTION 9 Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project? A. Project Risk Management B. Project Human Resource Management C. Project Scope Management D. Project Stakeholder Management Correct Answer: D QUESTION 10 Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter Correct Answer: A QUESTION 11 In which Knowledge Area is the project charter developed? A. Project Cost Management B. Project Scope Management C. Project Time Management D. Project Integration Management Correct Answer: D QUESTION 12 The ability to influence cost is greatest during which stages of the project? A. Early B. Middle C. Late D. Completion Correct Answer: A QUESTION 13 Which process involves developing an approximation of the monetary resources needed to complete project activities? A. Estimate Costs B. Control Costs C. Determine Budget D. Plan Cost Management Correct Answer: A QUESTION 14 Which tool or technique is used in the Develop Project Management Plan process? A. Pareto diagram B. Performance reporting C. SWOT analysis D. Expert judgment Correct Answer: D QUESTION 15 The organization's perceived balance between risk taking and risk avoidance is reflected in the risk: A. Responses B. Appetite C. Tolerance D. Attitude Correct Answer: A QUESTION 16 An output of the Manage Stakeholder Engagement process is: A. change requests B. enterprise environmental factors C. the stakeholder management plan D. the change log Correct Answer: A QUESTION 17 Which process numerically analyzes the effect of identified risks on overall project objectives? A. Plan Risk Management B. Plan Risk Responses C. Perform Quantitative Risk Analysis D. Perform Qualitative Risk Analysis Correct Answer: C QUESTION 18 Which Collect Requirements output links the product requirements to the deliverables that satisfy them? A. Requirements documentation B. Requirements traceability matrix C. Project management plan updates D. Project documents updates Correct Answer: B QUESTION 19 A temporary endeavor that creates a unique product or service is called a: A. Project B. Plan C. Program D. Portfolio

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller smartgrades. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $11.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

67096 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$11.49  17x  sold
  • (1)
  Add to cart