100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ALL CAPM Practice Exam (32 Sets) Questions with Verified Answers,100% CORRECT $35.49   Add to cart

Package deal

ALL CAPM Practice Exam (32 Sets) Questions with Verified Answers,100% CORRECT

PMBOK 6 CAPM Practice 53 Questions with Verified Answers,CAPM Practice Exam 150 Questions with Verified Answers,CAPM Practice Exam 55 Question with Verified Answers,CAPM Practice Test 31 Questions with Verified Answers,CAPM EXAM PREP 97 Questions with Verified Answers,CAPM PRACTICE Exam 89 QUESTION...

[Show more]
32 items

PMBOK 6 CAPM Practice 53 Questions with Verified Answers,100% CORRECT

(0)
$10.99

PMBOK 6 CAPM Practice 53 Questions with Verified Answers A project is said to be temporary because: A. it has a short duration B. it has a definite beginning and end C. it has the potential to be a continuous and ongoing effort D. its project team outlives it. - CORRECT ANSWER B. it has a def...

View example

CAPM Practice Exam 150 Questions with Verified Answers,100% CORRECT

(0)
$11.99

CAPM Practice Exam 150 Questions with Verified Answers 1. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called: - CORRECT ANSWER Management by Objectives 2. During the ful...

View example

CAPM Practice Exam 55 Question with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Practice Exam 55 Question with Verified Answers Management by Objectives - CORRECT ANSWER 1. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called: The bulk of the pro...

View example

CAPM Practice Test 31 Questions with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Practice Test 31 Questions with Verified Answers What is OPM3 - CORRECT ANSWER A PMI model designed to help organizations determine their level of maturity in project management (Organizational Project Management Maturity Model) Management by Obectives - CORRECT ANSWER process of establis...

View example

CAPM EXAM PREP 97 Questions with Verified Answers,100% CORRECT

(0)
$11.49

CAPM EXAM PREP 97 Questions with Verified Answers Initiation Process - CORRECT ANSWER Obtain authorization to start a new project or phase on an existing project Planning Process - CORRECT ANSWER Establish the scope of the project, refine the objectives and define the course of action required...

View example

CAPM Practice Exam 436 Questions with Verified Answers,100% CORRECT

(0)
$13.49

CAPM Practice Exam 436 Questions with Verified Answers Events that cannot occur together in a single trial are known as : - CORRECT ANSWER Mutually Exclusive A project that is experiencing constant Communication Blockers is most likely to - CORRECT ANSWER Have conflict occur A project manag...

View example

19 -CAPM Final Practice Exam 150 Questions with Verified Answers,100% CORRECT

(0)
$11.99

19 -CAPM Final Practice Exam 150 Questions with Verified Answers The processes required to define the scope of the project, refine the objectives, and determine the appropriate course of action to achieve the project objectives. A. Executing process group B. Monitoring and controlling proce...

View example

CAPM Exam Prep, PMI, PMBOK 6th Edition 1297 Questions with Verified Answers,100% CORRECT

(0)
$16.49

CAPM Exam Prep, PMI, PMBOK 6th Edition 1297 Questions with Verified Answers 360-degree appraisal - CORRECT ANSWER A performance review completed by a person's peers, manager, and subordinates. It's called a 360-degree appraisal as it's a circle of reviews by people at different levels of an or...

View example

CAPM PRACTICE Exam 89 QUESTIONS with Verified Answers,100% CORRECT

(0)
$11.49

CAPM PRACTICE Exam 89 QUESTIONS with Verified Answers For which of the following project management knowledge areas, accountability cannot be delegated by the project manager to someone else? A. Integration Management B. Schedule Management C. Cost Management D. Scope Management - CORRECT A...

View example

CAPM Practice Exam 163 Questions with Verified Answers,100% CORRECT

(0)
$11.99

CAPM Practice Exam 163 Questions with Verified Answers How many project management processes belong to the Planning Process Group? - CORRECT ANSWER 24 Who should be included in a project schedule development meeting? - CORRECT ANSWER Team members, sponsors, selected stakeholders, and those wit...

View example

CAPM Practice Exam 265 Questions with Verified Answers,100% CORRECT

(0)
$12.99

CAPM Practice Exam 265 Questions with Verified Answers Which of the following is the process of monitoring the status of the project to update the project schedule and manage changes to the schedule? - CORRECT ANSWER Control schedule Risk transference nearly often involves: - CORRECT ANSWER Pa...

View example

CAPM Practice Exam 430 Questions with Verified Answers,100% CORRECT

(0)
$13.29

CAPM Practice Exam 430 Questions with Verified Answers D. Throughout the project lifecycle - CORRECT ANSWER When should Project Risk Management be conducted? A. Project Planning B. Monitoring and Controlling C. Quality Planning D. Throughout the project lifecycle B. procurement strategy ...

View example

CAPM 7th Edition Practice Exam 22 Questions with Verified Answers,100% CORRECT

(0)
$10.89

CAPM 7th Edition Practice Exam 22 Questions with Verified Answers The issues you are facing on your project could have been predicted if a formal risk management process was used. Which document would have been most useful to you along the entire risk management process, from identifying risks to...

View example

CAPM PRACTICE EXAM 2|256 Questions with Verified Answers,100% CORRECT

(0)
$12.99

CAPM PRACTICE EXAM 2|256 Questions with Verified Answers The experiences of an organization's members are the basis for its _________. A. culture B. structure C. operations D. maturity - CORRECT ANSWER The experiences of an organization's members are the basis for its _________. ...

View example

CAPM Exam study guide 45 Questions with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Exam study guide 45 Questions with Verified Answers Acquire Project Team - CORRECT ANSWER <Process>. The process of confirming human resource availability and obtaining the team necessary to complete project assignments. Administer Procurements - CORRECT ANSWER <Process>. The ...

View example

CAPM PRACTICE EXAM 3|197 Questions with Verified Answers,100% CORRECT

(0)
$11.99

CAPM PRACTICE EXAM 3|197 Questions with Verified Answers "QUESTION NO: 1 Power, urgency and legitimacy are attributes of which stakeholder classification model? salience influence/impact power/interest power/influence - CORRECT ANSWER Power, urgency and legitimacy are attributes of which ...

View example

CAPM Practice Test 100 Questions with Verified Answers,100% CORRECT

(0)
$11.59

CAPM Practice Test 100 Questions with Verified Answers When is the Plan Risk Management process performed in a project? - CORRECT ANSWER Once or at predefined points in a project. Understanding, evaluating, defining, and managing requirements are essential to satisfying: - CORRECT ANSWER Custo...

View example

CAPM Practice Exam 151 Questions with Verified Answers,100% CORRECT

(0)
$11.99

CAPM Practice Exam 151 Questions with Verified Answers What includes the reasons for project initiation, objectives and a decision on the project? - CORRECT ANSWER Business Case Crashing - CORRECT ANSWER A technique used to shorten the schedule duration for the least incremental cost by adding...

View example

CAPM Practice Exam 2 - 4900 MGMT 51 Questions with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Practice Exam 2 - 4900 MGMT 51 Questions with Verified Answers Which process is used to implement approved change requests: - CORRECT ANSWER Monitor and Control Project Work Project roles and responsibilities are often documented in a RACI matrix. RACI is an acronym for: - CORRECT ANSWER ...

View example

CAPM Exam Ch 1|20 Questions with Verified Answers,100% CORRECT

(0)
$9.99

CAPM Exam Ch 1|20 Questions with Verified Answers Guide to project management body of knowledge PMBOK - CORRECT ANSWER The PMI publication that defines widely accepted project management practices. The CAPM and the PMP are based on the book Application areas - CORRECT ANSWER the areas of exper...

View example

CAPM Exam 1|100 Questions with Verified Answers,100% CORRECT

(0)
$11.49

CAPM Exam 1|100 Questions with Verified Answers You are a project manager for your company and are helping management choose a project. You've been presented with the following information: Project 1 has a net present value of $25,000 and will take five years to complete. Project 2 has a net pre...

View example

CAPM Exam 196 Questions with Verified Answers,100% CORRECT

(0)
$12.99

CAPM Exam 196 Questions with Verified Answers Cost Variance formula - CORRECT ANSWER Earned Value (EV) - Actual Cost (AC) What are the 6 constraints? - CORRECT ANSWER Scope, Risk, Resources, Quality, Schedule, Budget Initiating (Process Group) - CORRECT ANSWER Processes performed to define ...

View example

CAPM Certification: Ultimate CAPM Exam Prep 39 Questions with Verified Answers,100%CORRECT

(0)
$10.99

CAPM Certification: Ultimate CAPM Exam Prep 39 Questions with Verified Answers What are the 2 main characteristics of a project? - CORRECT ANSWER 1. Temporary; has a beginning and an end 2. Creates something unique i.e product, servic, or result - Ex: Constructing a building, creating a website...

View example

CAPM Practice 215 Questions with Verified Answers,100% CORRECT

(0)
$12.99

CAPM Practice 215 Questions with Verified Answers John is a project manager for a newly formed project team. The project team has worked hard for last 4 months and has taken very few leaves. John wants to motivate the team members by informing them that he can give a couple of paid leaves if they...

View example

CAPM Practice 172 Questions with Verified Answers,100% CORRECT

(0)
$12.99

CAPM Practice 172 Questions with Verified Answers Which of the following is a tool or technique used in the monitor communications process? - CORRECT ANSWER interpersonal and team skills what is the definition of work package? - CORRECT ANSWER the work defined at the lowest level of the work b...

View example

CAPM Practice Test One 50 Questions with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Practice Test One 50 Questions with Verified Answers There are three tools and techniques for the direct and manage project work process. One tool and technique will be meetings. What are the other two tools and techniques for directing and managing the project work? - CORRECT ANSWER Expert ...

View example

CAPM Practice Test Hard 77 Questions with Verified Answers,100% CORRECT

(0)
$11.39

CAPM Practice Test Hard 77 Questions with Verified Answers The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called: - CORRECT ANSWER management by objectives During the full ...

View example

CAPM Practice Exam 260 Questions with Verified Answers,100% CORRECT

(0)
$13.49

CAPM Practice Exam 260 Questions with Verified Answers 3 things that describe role of a PM ?? - CORRECT ANSWER 1. responsible for the final result of the team 2. need to integrate multiple disciplines 3. communicate with team Cost Management Plan has these 3 characteristics - CORRECT ANSW...

View example

CAPM EXAM TERMS 100 Questions with Verified Answers,100% CORRECT

(0)
$11.49

CAPM EXAM TERMS 100 Questions with Verified Answers Project - CORRECT ANSWER is a temporary endeavor undertaken to create a unique product, service or result. Definite beginning and an end. Project Management - CORRECT ANSWER is the application of knowledge, skills, tools and techniques to pro...

View example

CAPM Exam Prep 41 Questions with Verified Answers,100% CORRECT

(0)
$10.99

CAPM Exam Prep 41Questions with Verified Answers Develop Project Charter - CORRECT ANSWER Inputs: Project statement of work, business case, contract, enterprise environment factors, organizational process assets Outputs: Project Charter Identify Stakeholders - CORRECT ANSWER Inputs: Project C...

View example

CAPM Practice Test Series 4|25 Questions with Verified Answers,100% CORRECT

(0)
$9.99

CAPM Practice Test Series 4|25 Questions with Verified Answers One of the team members informed that optimistic estimate for an activity assigned to him will be 10 days and the pessimistic estimate will be 18 days. What is the realistic estimate? - CORRECT ANSWER Not known In a road constructi...

View example

CAPM Practice Test Series 5|25 Questions with Verified Answers,100% CORRECT

(0)
$10.49

CAPM Practice Test Series 5|25 Questions with Verified Answers Whose job is to resolve the competing interests and goals between parties of a project? - CORRECT ANSWER Project Manager Of the following, who is responsible for providing the funding of the project? - CORRECT ANSWER Sponsor A w...

View example
Show all
avatar-seller

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller paulhans. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $35.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

66579 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$379.88 $35.49
  • (0)
  Add to cart