NERC book quiz questions and answers latest 2023/24
  • NERC book quiz questions and answers latest 2023/24

  • Exam (elaborations) • 10 pages • 2023
  • NERC book quiz questions and answers latest 2023/24 You are an external BA with a frequency bais of 20 MW/.1 Hz that sees a frequency of 60.02 due to a large loss of load in the contingent BA. If your generator governor control systems responded to the frequency deviation approximately how much of a generation change would you BA experience? - -4MW Net actual interchange minus Net scheduled interchange is what? - Inadvertent interchange Suppose your interconnection operators at 59.97 Hz f...
    (0)
  • $9.99
  • + learn more
KNOWN NERC EXAM QUESTIONS FROM CLASS(FULLY SOLVED).
  • KNOWN NERC EXAM QUESTIONS FROM CLASS(FULLY SOLVED).

  • Exam (elaborations) • 11 pages • 2023
  • Available in package deal
  • A Balancing Authority notices that Operating Reserve has steadily declined throughout the hour. What is the most likely cause? a) Loss of a large generator in the area b) An inaccurate load forecast c) Loss of a major transmission line d) A malfunction of EMS b) An inaccurate load forecast Balancing Area A notices that the Interconnection frequency is 59.94 Hz and their ACE is 0. Which of the following could be the cause of this reading? a) A net under-generation in Balancing Ar...
    (0)
  • $14.49
  • + learn more
NERC EXAM QUESTIONS and ANSWERS 2023 SOLVED 100%
  • NERC EXAM QUESTIONS and ANSWERS 2023 SOLVED 100%

  • Exam (elaborations) • 7 pages • 2023
  • Available in package deal
  • A Balancing Authority notices that Operating Reserve has steadily declined throughout the hour. What is the most likely cause? a) Loss of a large generator in the area b) An inaccurate load forecast c) Loss of a major transmission line d) A malfunction of EMS - ANSWER-b) An inaccurate load forecast Balancing Area A notices that the Interconnection frequency is 59.94 Hz and their ACE is 0. Which of the following could be the cause of this reading? a) A net under-generation in Balancin...
    (0)
  • $10.99
  • + learn more
NERC BOOK QUIZ|QUESTIONS| WITH COMPLE SOLUTIONS 100% VERIFIED
  • NERC BOOK QUIZ|QUESTIONS| WITH COMPLE SOLUTIONS 100% VERIFIED

  • Exam (elaborations) • 13 pages • 2024
  • NERC BOOK QUIZ|QUESTIONS| WITH COMPLE SOLUTIONS 100% VERIFIED You are an external BA with a frequency bais of 20 MW/.1 Hz that sees a frequency of 60.02 due to a large loss of load in the contingent BA. If your generator governor control systems responded to the frequency deviation approximately how much of a generation change would you BA experience? - answer-4MW Net actual interchange minus Net scheduled interchange is what? - answerInadvertent interchange Suppose your interconnection ...
    (0)
  • $12.49
  • + learn more
KNOWN NERC EXAM QUESTIONS From Class (2023)
  • KNOWN NERC EXAM QUESTIONS From Class (2023)

  • Exam (elaborations) • 8 pages • 2023
  • Available in package deal
  • KNOWN NERC EXAM QUESTIONS From Class (2023) A Balancing Authority notices that Operating Reserve has steadily declined throughout the hour. What is the most likely cause? a) Loss of a large generator in the area b) An inaccurate load forecast c) Loss of a major transmission line d) A malfunction of EMS b) An inaccurate load forecast Balancing Area A notices that the Interconnection frequency is 59.94 Hz and their ACE is 0. Which of the following could be the cause of th...
    (0)
  • $15.49
  • + learn more
NERC book quiz Questions and Answers (100% Correct Elaborations)
  • NERC book quiz Questions and Answers (100% Correct Elaborations)

  • Exam (elaborations) • 29 pages • 2023
  • Available in package deal
  • You are an external BA with a frequency bais of 20 MW/.1 Hz that sees a frequency of 60.02 due to a large loss of load in the contingent BA. If your generator governor control systems responded to the frequency deviation approximately how much of a generation change would you BA experience? -4MW Net actual interchange minus Net scheduled interchange is what? Inadvertent interchange Suppose your interconnection operators at 59.97 Hz from one minute after midnight to noon and operate a...
    (0)
  • $10.49
  • + learn more
NERC book quiz questions (with solutions)
  • NERC book quiz questions (with solutions)

  • Exam (elaborations) • 13 pages • 2023
  • Available in package deal
  • You are an external BA with a frequency bais of 20 MW/.1 Hz that sees a frequency of 60.02 due to a large loss of load in the contingent BA. If your generator governor control systems responded to the frequency deviation approximately how much of a generation change would you BA experience? correct answers -4MW Net actual interchange minus Net scheduled interchange is what? correct answers Inadvertent interchange Suppose your interconnection operators at 59.97 Hz from one minute after midn...
    (0)
  • $11.49
  • + learn more
Practice Test NERC Questions and Correct Answers (GRADED A+)
  • Practice Test NERC Questions and Correct Answers (GRADED A+)

  • Exam (elaborations) • 48 pages • 2023
  • Available in package deal
  • A transmission line is operating with a voltage phase angle different of 30 degrees between the sending Vs and the receiving bus Vr. If the receiving end load is suddenly increased, the voltage phase angle difference will be? The phase angle will increase. When load is increased phase angle will increase. A load has a power factor of 0.9 lagging. If the load draws 100 MVA, what is the MW draw? 90 pf= mw/mva The high side of a delta-wye connection transformer is connected to a power s...
    (0)
  • $11.99
  • + learn more
NERC Reliability Coordinator- Vocabulary Exam 2024 Questions with Complete Solutions
  • NERC Reliability Coordinator- Vocabulary Exam 2024 Questions with Complete Solutions

  • Exam (elaborations) • 66 pages • 2024
  • NERC Reliability Coordinator- Vocabulary Exam 2024 Questions with Complete Solutions
    (0)
  • $13.29
  • + learn more
KNOWN NERC EXAM QUESTIONS: From Class with complete solution 2023
  • KNOWN NERC EXAM QUESTIONS: From Class with complete solution 2023

  • Exam (elaborations) • 7 pages • 2023
  • Available in package deal
  • KNOWN NERC EXAM QUESTIONS: From Class with complete solution 2023A Balancing Authority notices that Operating Reserve has steadily declined throughout the hour. What is the most likely cause? a) Loss of a large generator in the area b) An inaccurate load forecast c) Loss of a major transmission line d) A malfunction of EMS b) An inaccurate load forecast Balancing Area A notices that the Interconnection frequency is 59.94 Hz and their ACE is 0. Which of the following could be the ca...