Jim Burns, ISQS 4350, Final Exam; Questions & Answers 100% Solved
- Exam (elaborations) • 24 pages • 2024
- Available in package deal
-
- $12.99
- + learn more
Jim Burns, ISQS 4350, Final Exam; Questions & 
Answers 100% Solved 
In MS Project, which button do you click for subordination? 
a. Link 
b. Indent 
c. Resource Assign 
d. Resource Sheet Correct answer-b. Indent 
In MS Project, which button do you clink on to indicate precedence? 
a. Link 
b. Indent 
c. Resource Assign 
d. Resource Sheet Correct answer-a. Link
-
ISQS Burns 4350 Final Exam (100% correct and graded A+)
- Exam (elaborations) • 11 pages • 2024
- Available in package deal
-
- $7.99
- + learn more
(According to Goldratt...) 
Team players put too much ____ into their estimated durations - Safety 
A task has a budget of $20,000 and a schedule duration of 5 days. Given an EV of $6,000 and a PV of 
$12,000 
What is the task's SV (schedule variance)? 
Is the task ahead or behind schedule? - - $6,000 
- The task is deeply behind schedule 
A task has a budget of $20,000 and a scheduled duration of 5 days 
If day 3 has just transpired, what is the PV, the BCWS? - $12,000 
A task has a budget of ...
-
ISQS 4350 (Burns) Exam 2 Questions and Solutions
- Exam (elaborations) • 64 pages • 2024
- Available in package deal
-
- $14.49
- + learn more
Which of the following statements is false? 
 
a. Probability distributions for PERT activity durations are represented by use of the Beta distribution. 
b. A forward pass through a project network diagram determines the early start and early finish dates for each activity. 
c. To complete a project it is necessary to complete all tasks on all paths through the project network. 
d. The critical path is the series of activities that determine the earliest time by which a project can be started. 
...
-
ISQS 4350 (Burns) Exam 2 Questions and Correct Answers the Latest Update and Recommended Version
- Exam (elaborations) • 77 pages • 2024
-
- $14.49
- + learn more
Which of the following statements is false? 
a. Probability distributions for PERT activity durations are represented by use of the Beta 
distribution. 
b. A forward pass through a project network diagram determines the early start and early 
finish dates for each activity. 
c. To complete a project it is necessary to complete all tasks on all paths through the project 
network. 
d. The critical path is the series of activities that determine the earliest time by which a project 
can be star...
-
ISQS 4350 Exam 2Questions with Correct Solutions Best Rated A+
- Exam (elaborations) • 28 pages • 2023
-
- $11.99
- + learn more
ISQS 4350 Exam 2Questions with Correct Solutions Best Rated A+
And that's how you make extra money
-
ISQS 4350 (Burns) Exam 2 Questions and Answers | 100% Pass
- Exam (elaborations) • 67 pages • 2024
-
- $12.49
- + learn more
ISQS 4350 (Burns) Exam 2 Questions 
and Answers | 100% Pass 
Which of the following statements is false? 
a. Probability distributions for PERT activity durations are represented by use of the 
Beta distribution. 
b. A forward pass through a project network diagram determines the early start and 
early finish dates for each activity. 
c. To complete a project it is necessary to complete all tasks on all paths through the 
project network. 
d. The critical path is the series of activities that de...
-
ISQS 4350 (Burns) Exam 2 Questions and Correct Answers | Latest Update
- Exam (elaborations) • 79 pages • 2024
-
- $13.49
- + learn more
Which of the following statements is false? 
a. Probability distributions for PERT activity durations are represented by use of the Beta 
distribution. 
b. A forward pass through a project network diagram determines the early start and early 
finish dates for each activity. 
c. To complete a project it is necessary to complete all tasks on all paths through the project 
network. 
d. The critical path is the series of activities that determine the earliest time by which a project 
can be star...