A significant difference between "planning" and "scheduling" is, - Answer Scheduling 
determines when to do, and planning determines what to do, how to and by whom. 
What is NOT true about an activity? - Answer An activity usually does not need to be 
measurable 
There is an activity, installing exterior sheathing. A crew can install 1,200 sf per day, and 
the total quantity is 3,200 SF. What is the duration of this activity? - Answer 3 days
-
CM 4101 Midterm Exam Questions Solved 100% Correct
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $11.49
- + learn more
what is not true about an event - Answer an event usually consumes resources. 
an event usually takes time. 
major types of activities - Answer procurement, production/construction, 
management 
The conditions of limited resource availability dictate certain activities cannot be 
performed simultaneously. This is: - Answer resource constraint
-
CM 4101 Exam Prep Test Questions Answered 100% Correct
- Exam (elaborations) • 4 pages • 2024
- Available in package deal
-
- $11.49
- + learn more
Starting a new project in P6 you must first: - Answer File - Close All 
3 Establishing Relationships - Answer Finish-to-start, Start-to-start, Finish-to-finish 
Finish-to-start (FS) - DEFAULT - Answer A finishes, B can start 
Start-to-start (SS) - Answer A starts, B can start