A project estimator is developing a cost estimate for construction of a new diagnostic
imaging wing. The following costs are estimated:
Fixed equipment installation cost is $700,000
Site preparation is $50,000
Utilities costs per year is $425,000
Construction material costs is $1,200,000
Portable equipment is $900,000
Annual depreciation is $275,000
What are the expected contractor costs? - ANSWER 1,600,000
Which of the following are components of common general contractor markups:
1. Permit and inspection fees
2. General conditions
3. Overhead and profit
,4. Site condition assessment fees - ANS 2, 3, and 4
Demand side management (DSM) programs are designed and offered to organizations
by energy providers to do which of the following during peak service? - ANS Provide
emergency energy demand sources
When designing a preventive maintenance program, a facility manager should attempt
to have an annual test run on each needed battery-powered lighting system. The test
should be run for NOT less than: - ANSWER 30 seconds
In existing facilities, doors which open onto exit corridors shall be 1-3/4 inch solid
bonded wood core or be of other construction that resists fire for NOT less than: -
ANSWER 20 minutes
Total dissolved solids in a cooling tower are maintained by: - ANSWER Variable speed
drive fans
Which of the following contract types requires there be a schedule of values used during
pricing? - ANSWER Guaranteed maximum price
A project has an approved budget of $6,600,000. The fees for planning and design are
forecasted at $700,000 and the construction costs are forecasted at $5,100,000. What is
the dollar value of a 10% construction contingency? - ANSWER 580,000
The Joint Commission requires an organization to develop and implement a policy that
prohibits smoking except in those circumstances that are specified. The intent of this
standard is to help reduce risks in regards to:
1. Possible adverse effects on care, treatment, and services to people who smoke
2. Passive smoke to others
, 3. Fire
4. False alarms - ANSWER 2, 3, and 4
An organization chooses to put in place and implements appropriate controls when
planning demolition, construction, or renovation to mitigate risk and minimize the
impact of these activities on infection control. Which are proper controls within the area
of actual construction:
1. Negative air machines
2. Dust barriers
3. Wet-mopping the floors
4. Job site free of debris - ANSWER 2, 3 and 4
A facility is installing an air intake for a medical air compressor. At what minimum
heights, in ft., should this be located above the ground? ANSWER 5
When load testing an Emergency Power Supply System, EPSS with a load bank since the
-required monthly test could not reach 30% of the name plate load rating, the minimum
duration of the test shall be: - ANSWER 30 minutes
The contractor close-out of a hospital construction project would include:
1. A punch list
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Braxton. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.99. You're not tied to anything after your purchase.