100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
NICET LEVEL 1 HIGHWAY CONSTRUCTION EXAM WITH COMPLETE SOLUTIONS 100% COMPLETE $12.99   Add to cart

Exam (elaborations)

NICET LEVEL 1 HIGHWAY CONSTRUCTION EXAM WITH COMPLETE SOLUTIONS 100% COMPLETE

 5 views  0 purchase
  • Course
  • NICET LEVEL 1 HIGHWAY CONSTRUCTION
  • Institution
  • NICET LEVEL 1 HIGHWAY CONSTRUCTION

NICET LEVEL 1 HIGHWAY CONSTRUCTION EXAM WITH COMPLETE SOLUTIONS 100% COMPLETE Substantial Completion - Answer- When all work is complete, with the exception of landscaping Items listed in 811.04, removal of SESC measures, FINAL CLEANUP, and repair of unacceptable work; provided the RE has determi...

[Show more]

Preview 2 out of 7  pages

  • November 8, 2024
  • 7
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • NICET LEVEL 1 HIGHWAY CONSTRUCTION
  • NICET LEVEL 1 HIGHWAY CONSTRUCTION
avatar-seller
Scholarsstudyguide
NICET LEVEL 1 HIGHWAY CONSTRUCTION
EXAM WITH COMPLETE SOLUTIONS 100%
COMPLETE

Substantial Completion - Answer- When all work is complete, with the exception of
landscaping Items listed in 811.04, removal of SESC measures, FINAL CLEANUP, and
repair of unacceptable work; provided the RE has determined that: 1. The Project is
safe and convenient for use by the public. 2. Failure to complete work and repairs
excepted above will not result in the deterioration of other completed work. 3. The value
of the remaining landscaping work, removal of SESC measures, repairs, and FINAL
CLEANUP is less than 2 percent of the Total Adjusted Contract Price.

Superintendent - Answer- The Contractor's authorized representative responsible for
and in charge of the Work and is authorized by the Contractor to receive all
communications from the Department.

Surety. - Answer- The individual, partnership, or corporation, other than the Contractor,
that has provided a proposal bond, a performance bond, or a payment bond.

Testing Agency - Answer- A privately-owned facility capable of testing and evaluating
component parts, or the whole, for certification of the composition or construction of the
material or product. Must be an AASHTO-accredited laboratory for each field of
accreditation and type of material to be tested

Total Adjusted Contract Price - Answer- The Total Contract Price as it is adjusted
through the issuance of Change Orders and the calculation of as-built quantities.

Total Contract Price - Answer- The correctly determined summation of lump sum bids
and products of all quantities for Items shown in the Proposal multiplied by the unit
prices bid.

traveled way - Answer- . The portion of the roadway for the movement of vehicles
exclusive of shoulders and auxiliary lanes (see Figure 101-1).

Utility - Answer- The company, agency, or other entity that provides services, including,
but not limited to: electric, water, gas, sewer, fiber optic, communications, and railroad,
and the Department with regard to ITS and electrical facilities.

, utility - Answer- The rails, lines, facilities, or systems owned by Utilities

Work - Answer- Labor, services, materials, equipment, tools, transportation, supplies,
and incidentals necessary or convenient for Completion by the Contractor of the
construction described in the Contract and the carrying out of all duties and obligations
imposed by the Contract wholly, or any portion thereof, on the Contractor.

work - Answer- Particular elements, Items, or portions of the Work.

working day - Answer- Any day, exclusive of: 1. Saturdays, Sundays, and holidays. 2.
Days on which the Contractor is specifically required by the Contract to suspend
construction operations. 3. Days on which the Contractor is prevented by any conditions
beyond the control of the Contractor and adverse to the current controlling operation or
operations, as determined by the RE, from proceeding with at least 75 percent of the
normal labor and equipment force engaged on such operation or operations for at least
60 percent of the total daily time being currently spent on the controlling operation or
operations for all shifts.

working drawings - Answer- Stress sheets, shop drawings, catalogue cuts, calculations,
diagrams, illustrations, schedules, performance charts, brochures, and other
supplementary plans or similar data prepared by the Contractor or subcontractors,
manufacturers, suppliers, or distributors.


Acceptance - Answer- The written acceptance by the Department of the Work.

acceptance testing - Answer- Testing conducted by the Department to measure the
degree of compliance to the Contract

actual cost - Answer- The computed cost using calculations provided

addendum - Answer- A Contract revision or response to a Contractor inquiry issued
after advertisement and before the opening of bids.

as-built quantity - Answer- The quantity of a completed Item eligible for payment

authorized funding amount - Answer- The amount of funds authorized by the
Department for the Contract

Bidder - Answer- The individual, firm, partnership, corporation, joint venture, or any
acceptable combination thereof that submits a bid to the Department.

bridge - Answer- . A structure, other than a culvert, including supports, erected over a
depression or an obstruction, such as water, highway, or railway, and having a track or
passageway for carrying traffic or other moving loads and having a length 3 measured
along the center of the structure of more than 20 feet between undercopings of

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Scholarsstudyguide. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78252 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.99
  • (0)
  Add to cart