Using the information provided in figure 9a, 9b, and 9c, what is the Total Projected Labor cost at Completion for the Concrete Footings?
A. 81.41
B. 803.84
C. 5,150.72
D. 1,0615.00 - Answer-c
Using the information provided in fi...
PRACTICE TEST AIC STUDY GUIDE
QUESTIONS WITH CORRECT
ANSWERS
Using the information provided in figure 9a, 9b, and 9c, what is the Total Projected
Workhours at Completion for the Column Forms?
A. 27
B. 104
C. 602
D. 2,472 - Answer-c
Using the information provided in figure 9a, 9b, and 9c, what is the projected gain or
loss in Workhours for the Column Forms?
A. (174)
B. 325
C. 1,897
D. 2,396 - Answer-a
Using the information provided in figure 9a, 9b, and 9c, what is the Budgeted Labor Unit
Cost in Dollars per unit for the Concrete Footings?
A. 0.047
B. 21.45
C. 137.25
D. 256.00 - Answer-b
Using the information provided in figure 9a, 9b, and 9c, what is the Week Labor Unit
Cost in Dollars per unit for the Concrete Footings?
A. 0.70
B. 1.43
C. 3.14
D. 14.60 - Answer-d
Using the information provided in figure 9a, 9b, and 9c, what is the To Date Labor Unit
Cost in Dollars per unit for the Concrete Footings?
A. 0.32
B. 3.14
C. 20.12
D. 5,125.00 - Answer-c
Using the information provided in figure 9a, 9b, and 9c, what is the Total Projected
Labor cost at Completion for the Concrete Footings?
,A. 81.41
B. 803.84
C. 5,150.72
D. 1,0615.00 - Answer-c
Using the information provided in figure
9a, 9b, and 9c, what is the projected gain or loss in Labor Dollars for the Concrete
Footings?
A. (1.20)
B. (4,685.00)
C. 338.00
D. 5,452.46 - Answer-c
Using the information provided in figure 9a, 9b, and 9c, what is current projection for the
quantities in Vertical Lineal Feet (VLF)?
A. 680
B. 5,300
C. 5,980
D. 6,700 - Answer-c
How should the nodes on a logic network be numbered?
A. Consecutively
B. Separated by a minimum of five
numbers
C. The preceding node is greater than
the following node
D. The following node is greater than
the concurrent node - Answer-b
How is Free Float defined?
A. The amount of slack in a node
B. The amount of slack between
activities
C. The amount of slack within a path
(series) of activities
D. The amount of slack accumulated
throughout the logic network - Answer-b
What types of activities are considered first when shortening the length of a project?
A. Zero float and least cost
B. Zero float and highest costs
C. Highest floats and least cost
D. High floats and highest costs - Answer-a
How is the term fast tracking defined in construction?
A. Planning and Scheduling the design
, B. Overlapping execution of the
construction activities
C. Finalizing the design and
procurement before construction
begins
D. Overlapping execution of the
design, procurement and construction - Answer-d
What is the name of the term for shifting the activities within their available free floats in
order to produce a uniform work force and reduce the maximum resource usage
requirements?
A. Crashing
B. Crew Utilization
C. Resource Leveling
D. Time scaled Networking - Answer-c
What is the best source for developing the activity descriptions for the logic network and
schedule?
A. General Requirements
B. Technical Specifications
C. Financial Reports and the Balance
Sheets
D. Estimate and earned workhouse report - Answer-b
How is Total Float defined?
A. The amount of slack
B. The amount of slack
activity
C. The amount of slack
(series) of activities
D. The amount of slack throughout the logic
in a node within an
within a path
accumulated network - Answer-c
For a Design-Build Schedule to be admissible evidence in court, it must contain the
Design Activity Sequence, Procurement Activity Sequence and the Construction Activity
sequence. Which of the following must also be on the preliminary schedule?
A. A bar-chart with owner-furnished items and planned weather losses each month
B. A time scaled with owner-furnished items and planned weather losses at the end
C. A bar-chart with planned versus as-built activities, sequence changes & all delays
D. A time scaled with owner-furnished items and planned weather losses each month -
Answer-d
Using the information provided in figure 10, what is the total number of days to complete
this sequence of activities?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller victoryguide. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $12.89. You're not tied to anything after your purchase.