A cumulative list of job deficiencies/rework items can be found in: - ANSA deficiency tracking
system/reworks items list.
Actual construction on the job site begins: - ANSAfter an interim or final QC Plan is
accepted.
All submittals for government approval must be provided by the _________________ in time
to allow for the review, approval, procurement, delivery, and performance of preparatory
phase for an item before it is needed for construction. - ANSContractor to the Government
An effective contractor quality control program will: - ANSBe an incentive for work to be done
correctly the first time resulting in earlier completion, reduced field overhead costs, and
greater profits.
Characteristics that describe a definable feature of work include: - ANSCross-referenced
listings to the contractors construction schedule that may have more than one definable
feature under a section of the specifications.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - ANSAccording to plans and specifications, on time, within a
defined budget and a safe work environment.
Contractor testing procedures: - ANSAre outlined in the Quality Control Plan as defined by
Section 01450N/01451A and addressed at the Coordination and Mutual Understanding
Meeting (Navy).
Design-Build contracts require: - ANSThe QC Manager to be in place and take an active role
in the review and coordination of the design.
During the punch-out inspection of a project: - ANSQuality Assurance Personnel must
assure that the contractor prepares a punch-list and makes corrections.
ENG Form 4288-R, the submittal register: - ANSIdentifies those submittals requiring
government approval
Grounds for withholding payment include the contractors failure to: - ANSPerform in
accordance with the terms of the contract, provide a Quality Control Plan giving assurance of
intent and ability to comply with quality standards, and build to the quality standards
established by the contract.
If initial review of the quality control plan shows it to be unacceptable: - ANSThe contractor
makes changes before acceptance.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Qualitydocs. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.99. You're not tied to anything after your purchase.