The 1970's law that set into place the regulation of stormwater is: -answer/ The
Clean Water Act
Requirements for managing stormwater activity on a construction site are outlined
in the following regulation: -answer/ NPDES
Which of the following is never an allowable stormwater discharge from a
construction site? -answer/ Discharge from contaminated groundwater
The Notice of termination can filed when: -answer/ All construction activity, inside
and outside the building, is complete and permanent stabilization verified
Relative to stormwater permitting, all of the following must occur before
construction starts except: -answer/ Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water infiltration, dissipates
rainfall energy and slows overland flow of stormwater -answer/ Vegetation
Of the following factors that influence erosion rates, the one a contractor has the
most control over is: -answer/ Groundcover
Temporary stabilization should be implemented -answer/ Immediately on all
disturbed areas that are likely to or will remain inactive for 14-days or more
, The Primary purpose of a construction exit is -answer/ To remove sediment from
construction site vehicles and minimize trackout
Common types of erosion include all of the following except -answer/
Sedimentation
Which of the following is NOT a beneficial use of water? -answer/ Flushing a spill
down a storm drain
When installing and maintaining a check dam make sure: -answer/ The low point
(overflow) of the check dam is in the middle of the channel
To reduce the possibility of undercutting in channels, you should: -answer/ Install
filter fabric under rock and similar materials placed within the stormwater
The good housekeeping section of the SWPPP must include all BUT which of the
following -answer/ Post construction stormwater management procedures
Runoff Controls include all but which one of the following -answer/ Rolled
Erosion Control Products
Proper spill management should include all of the following EXCEPT: -answer/
Installation of a spill pit on your construction sites
The best location for portable toilets on your construction site is -answer/ on level
ground, in low construction traffic areas
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller tutorWADE. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $13.49. You're not tied to anything after your purchase.