When testing a water level supervisory switch serving a pressure tank a signal shall indicate if the water level _____________from the required level
(NFPA 72, Table 14.4.3.2 17 (j) (4) - correct answer. rises or falls ...
Nicet Level 1 Study Guide Questions And
Answers 100% Verified.
When testing a water level supervisory switch serving a pressure tank a signal shall
indicate if the water level _____________from the required level
(NFPA 72, Table 14.4.3.2 17 (j) (4) - correct answer. rises or falls over 3 inches
If combination audible/visible appliances are installed the location of the installed
appliance shall be determined by the requirements of _______.
(Nfpa 72 18.4.8.1) - correct answer. the visible appliance
What is the maximum number of 12 gauge THHN wires that can be installed in 1" EMT?
(Nec Annex C tables) - correct answer. 26
Two resistors are connected in parallel. R1 = 300 Ohms, R2 = 300 Ohms. What is their
equivalent resistance? - correct answer. 150 ohms
A Room is 200' long and 150' wide and the 8' high ceiling is smooth and flat. A spot type
heat detector has been selected that is listed for a 50' maximum spacing between
detectors. According to NFPA 72 how many detectors will be needed to protect this
room?
x = - correct answer. 12
According to NFPA 72 the minimum number of restorable fixed temperature spot type
heat detectors that must be tested during each annual test is?
, (NFPA 72 14.4.4.5.1) - correct answer. Two detectors or more on each initiating
device circuit
According to NFPA 72 how many spot type heat detectors are required for a space that
is 80' long and 55 floor wide with a smooth 10' ceiling? the detector is listed for a
maximum space between detectors of 30' - correct answer. 6
What color code requirement for a spot type heat detector rated at 200゚F - correct
answer. White (NFPA 72, Table 17.6.2.1)
Unless otherwise recommended by the manufacturers published instructions single and
multiple stations smoke alarms installed in one and 2 family dwellings shall be replaced
every - correct answer. 10 years from the day-of manufacture. (NFPA 72, 14.4.7.1)
Fire alarm cables are permitted to be strapped to conduit to support the cable - correct
answer. False (NEC 760.143)
Where non power limited wiring is installed exposed it must be mechanically protected
within_____of the finished floor - correct answer. 7' ft
Fire-Warning equipment to be installed in residential occupancies shall produce the
audible emergency evacuation signal described in - correct answer. ANSI S3.41
According to NFPA 72, visible notification appliance for non-sleeping areas must be
mounted between ___ and ___ inches above the finished floor - correct answer. 80 &
96
If system impairment occurs, the owner must be notified ___ within ___ - correct
answer. in writing & within 24 hours
A 20 X 20' ft room with a 20'ft high ceiling requires at a minimum a ___ ceiling mounted
strobe - correct answer. 30 candela
According to NFPA 72, a 40 x 40'ft room or area with a 10'ft ceiling is best covered by a
___ cd visible notification appliance, centered on one wall. - correct answer. 60
Conductors returning to the fire alarm control panel (FACP) from the last field device on
the circuit might indicate a _____ circuit - correct answer. Class A
Secondary power supplies for an emergency voice/alarm communication fire alarm
system shall be capable of operating for minimum of ___ of standby followed by ___ of
alarm. - correct answer. 24 hrs & 15 mins
The fire alarm system primary power branch circuit disconnecting means must be ___ in
color. - correct answer. Red
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller techgrades. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $10.99. You're not tied to anything after your purchase.