State one reason why an earth fault-loop impedance test is carried out on
the socket outlet furthest from the main switchboard in a low voltage
electrical installation?
✔✔Any ONE of:
● To confirm that the electrical protection for the final subcircuit will
operate within the required time.
● To confirm that the electrical protection all other final subcircuits
supplied from the main switchboard will operate with the required time.
Define the term cut off characteristic as it applies to an HRC fuse.
✔✔This is the value of fault current that cuts off (operates) the fuse that
is less than the prospective short-circuit current.
A three-phase induction motor is controlled by a star/delta starter that
incorporates thermal overloads.
State one reason why HRC fuses are installed at the origin of the final sub
circuit supplying the induction motor.
✔✔To provide short-circuit fault protection to both the final sub circuit
and the motor
,State one hazard that could occur when disposing of low-pressure or
high-pressure sodium-vapour lamps
✔✔Any ONE of:
● Fire risk (sodium + moisture produces hydrogen)
● Risk of chemical burns (sodium + water produces sodium hydroxide
(caustic soda))
When the load on a transformer changes from no-load to full-load a
voltage drop occurs at the secondary terminals.
Is this voltage drop normal?
State a reason to support your answer
✔✔Yes
Because of the current flow through the impedance of the windings
This is a block diagram of a three-phase circuit to a three-phase star-
connected hot water cylinder in a factory.
Switchboard - lockable isolator - contactor - HWC
HRC fuses protect the final sub circuit to the three-phase HWC.
, The existing hot water cylinder is to be removed . The new cylinder will
be installed once building alterations have been completed
Describe how to isolate the existing hot water cylinder
✔✔The description must show:
- opening the isolator or removing the fuses
- doing a voltage test at the load side of the isolator (or the supply side of
the contactor).
- Using the prove-test-prove method to confirm isolation has occurred
- locking the isolator open
-attaching a danger tag to the isolator
Building alterations have been completed. A new correctly-rated flexible
cable has been connected to the new hot water cylinder.
State TWO instrument tests that must be carried out on the new flexible
cable and hot water cylinder to ensure that they are safe to connect to the
electricity supply.
✔✔Earth continuity test
Insulation resistance test
State ONE reason why rectified three-phase a.c. Is easier to smooth with
filters, than rectified single-phase a.c.
✔✔Ensure the circuit is still isolated by using the prove-test-prove
method.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller saraciousstuvia. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $16.19. You're not tied to anything after your purchase.