Asphalt Paving LEVEL 2 QUESTIONS AND ANSWERS. LATEST UPDATES What materials are approved for use for tack application? A. SS-1 or CSS-1, SS-1H or CSS-1H B. RS-1, RS-2, MC-250, SS-4 C. RS-1h, RS-2, CRS-1h, NTSS-1hm, RA-500 D. All the Above E. None of the Above - ANSWER (C.) RS-1h...

[Show more]

Preview 2 out of 14  pages

  • August 31, 2024
  • 14
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • Asphalt Paving LEVEL 2
  • Asphalt Paving LEVEL 2
avatar-seller
TheExamMaestro
Asphalt Paving LEVEL 2 QUESTIONS
AND ANSWERS. LATEST UPDATES
What materials are approved for use for tack application?
A. SS-1 or CSS-1, SS-1H or CSS-1H
B. RS-1, RS-2, MC-250, SS-4
C. RS-1h, RS-2, CRS-1h, NTSS-1hm, RA-500
D. All the Above
E. None of the Above - ANSWER (C.) RS-1h, RS-2, CRS-1h, NTSS-1hm, RA-500

The minimum air temperature (in the shade away from artificial heat) for a 1.5 inch
layer of asphalt is:
A. 40°F
B. 45°F
C. 50°F
D. 65°F and rising - ANSWER (A.) 40°F

A quality of Asphalt Mix will be:
A. Constructable
B. Conform to specifications
C. Satisfy the functional requirements
D. All the above - ANSWER (D. All the above) - Constructable, conform to
specifications, and satisfy the functional requirements

Which condition will result in more time available for compaction?
A. SP-19 coarse mix during the day
B. FC-9.5 fine mix at night
C. FC-9.5 coarse mix during the day
D. SP-12.5 fine mix with PG76-22 - ANSWER (A.) SP-19 coarse mix during the day

The fallowing statement is true about trucks used to haul asphalt mix:
A. Truck drivers must be certified to haul asphalt mix
B. Truck beds need to be clean and smooth
C. Hole must be present in both sides of truck bed
D. All the above
E. Both B & C - ANSWER (E. Both B & C) - Truck beds need to be clean and smooth
and hole must be present in both sides of the truck bed

When using a vibratory roller, which is generally correct?
A. Keep the roller frequency high and impact spacing between 10-12 impacts per foot
B. Run low frequency, high amplitude, and 10-12 impacts per foot
C. Vibrate only when the lift of mix is less than 1.25 inches
D. Both A and C

, E. Both B and C - ANSWER (B.) Run low frequency, high amplitude, and 10-12 impacts
per foot

If the desired spread rate is 165 lbs/sq yds for SP mix, what is the construction
tolerance for the layer thickness? - ANSWER -+ 8.3 lbs/sq yds

On the structural layer prior to the friction course, correct any deficiencies before
placing the friction course.
A. Greater than 3/16"
B. Equal to 3/16"
C. Less than 1/8"
D. Greater than 1/8" - ANSWER Equal to 3/16"

The standard Lot size for FC-5 is:
A. 500 to 1000 tons
B. A day's production
C. 1000 feet
D. 2000 tons
E. 4000 tons - ANSWER (D.) 2,000 Tons

Milling can help:
A. Restore curb reveal
B. Remove cracks in the existing pavement
C. Improve the ride
D. Change the cross slope
E. All the above - ANSWER (E. All the above) - Restore curb reveal, remove cracks in
the existing pavement, improve the ride, and change the cross slope.

Truck beds need to be coated with release agent:
A. Each time they are loaded
B. Only when they are dirty
C. As needed to prevent the asphalt from sticking
D. All of the above - ANSWER (C.) As needed to prevent the asphalt from sticking

Given: The average sublot density (Gmb) of the roadway cores is 2.223 and the Gmm
for the same sublot is 2.400. The target spread rate was 162 lbs/sq yds. What is the %
of Gmm density for the sublot? - ANSWER 92.6%

(Y/N:) If a Contractor's Quality Control Core Gmb test is 2.225 and the Verification test
on the same ore Gmb test is equal to 2.205, do these two values compare? - ANSWER
Yes

If roadway density values are decreasing throughout the shift, the possible cause could
be:
A. Not enough trucks on the project
B. Plant production rate cant keep up

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller TheExamMaestro. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75323 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.99
  • (0)
  Add to cart