100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CM 1011 Final Test Questions And Answers $14.49   Add to cart

Exam (elaborations)

CM 1011 Final Test Questions And Answers

 3 views  0 purchase
  • Course
  • CM 1011
  • Institution
  • CM 1011

CM 1011 Final Test Questions And Answers

Preview 3 out of 17  pages

  • August 31, 2024
  • 17
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • CM 1011
  • CM 1011
avatar-seller
Zanaya
CM 1011 Final




The pre-construction meeting should include discussion about schedule issues. - Answer -True



A change order adjustment amount does not include general overhead and profit. - Answer -False



A claim can only be made after the project is complete. - Answer -False



The two key process tools used to track all inquiries, decisions, and approvals that occur during
construction are the requests for information (RFI'S) and submittals. - Answer -True



Managing the many changes on a project is one of the contract administration functions. - Answer -True



Contract administration is all about managing the business details and relationships. - Answer -True



Liquidated damages is an agreed upon amount per day for the project finishing late. - Answer -True



Steel beams are an example of a construction product that requires a shop drawing. - Answer -True

,Major subcontractors and vendors do not need to attend a pre-construction meeting. - Answer -False



Retainage is an amount retained by the owner from progress payments as a penalty for mistakes made
by the contractor. - Answer -False



Once a progress payment is received by the prime contractor it is obligated to promptly pay its
subcontractors and vendors. - Answer -True



A time extension is a contract adjustment used when a monetary adjustment is not owed. - Answer -
False



A project is considered totally complete even if paperwork has not been delivered to the owner. -
Answer -False



Entry-level CM's are seldom, if ever, used to keep up with RFI's. - Answer -False



The first task in contract administration is to create a contact list for every single person associated with
the project. - Answer -True



A project may go forward without paperwork. - Answer -False



Arbitration can be more expensive than litigation. - Answer -True



Partnering is a concept involving only the owner and prime contractor. - Answer -False



The schedule of values represents the owner's budget. - Answer -True



One of the reasons for a pre-construction meeting is to clarify the lines of authority and communication.
- Answer -True

, One of the least important contract administration functions is the contractor getting paid on time. -
Answer -False



Each time number in a network diagram represents a calendar day, not a work day. - Answer -False



Sequencing of activities is not the same as network logic. - Answer -False



Assigning durations to each activity precedes sequencing. - Answer -False



Some production activities do not actually require any physical effort. - Answer -True



Predicting durations is an exact science. - Answer -False



A short-interval schedule is not the same as a look-ahead schedule. - Answer -False



The three types of activities that must be planned and included in a schedule are: pre-construction,
construction operations, and post-construction. - Answer -False



The primary tool associated with project planning is the estimate. - Answer -False



Summary schedules group activities under broader headings such as mobilization, site work, foundation,
and rough framing. - Answer -True



A network diagram is nothing more than a work plan. - Answer -True



Each time number in a network diagram represents a calendar day, not a work day - Answer -False



The three stages of a precedence diagram schedule are planning, sequencing, and scheduling. - Answer -
True

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Zanaya. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $14.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75759 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$14.49
  • (0)
  Add to cart