100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
WGU Project Management C722 Unit 8 Module 30 questions and answers verified 2024 $13.49   Add to cart

Exam (elaborations)

WGU Project Management C722 Unit 8 Module 30 questions and answers verified 2024

 4 views  0 purchase
  • Course
  • WGU C722
  • Institution
  • WGU C722

WGU Project Management C722 Unit 8 Module 30 questions and answers verified 2024

Preview 2 out of 11  pages

  • August 28, 2024
  • 11
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • WGU C722
  • WGU C722
avatar-seller
LEWISSHAWN55
WGU Project Management C722 Unit 8
Module 30
What occurs when the project team integrates enhancements to the scope
without proper evaluation and approval?


a. Project compression


b. Scope creep


c. Resource reassignment


d. Project failure - correct answer ✔b. scope creep
When a project team integrates enhancements without proper evaluation and
approval, scope creep occurs.


A project manager is monitoring the project schedule and has already
compared WBS activities to the schedule baseline. What should the project
manager do next?


a. Revise the baseline scope


b. Implement schedule changes


c. Analyze variances - correct answer ✔c. Analyze variences
The process of monitoring a project schedule involves comparing WBS
activities to the schedule baseline, analyzing variances, and then proposing
changes to the schedule or plan.

, ____________ may be caused by errors in estimating the activity durations.
a. work performance data
b. variances
c. baseline scope - correct answer ✔b. variances
Variances may be caused by errors in estimating the activity durations.


True or False:
Project scope is fixed at the conclusion of the project planning phase. - correct
answer ✔False:Project scope is baselined at the conclusion of the project
planning phase.


What is the process of assessing the work completed called?


a. Scope creep


b. Earned Value Analysis (EVA)


c. Risk management


d. Baselining - correct answer ✔b. Earned Value Analysis (EVA)
EVA is the process of assessing the work completed. Using EVA allows the
project manager to compare the actual WBS work activities completed to the
actual expenditures.


True or False:
A project manager should change the baseline scope whenever project
enhancements are approved and implemented. - correct answer ✔False:

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller LEWISSHAWN55. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75759 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.49
  • (0)
  Add to cart