RWP PG QUESTIONS & ANSWERS
type of working limits on controlled track - CORRECT ANSWER-foul time,
exclusive track occupancy
type of working limits on non-controlled track - CORRECT
ANSWER-inaccessible track
type of train approach warning - CORRECT ANSWER-watchman
type of train approach warning - CORRECT ANSWER-individual train detection
What type of work roadway workers do? - CORRECT ANSWER-inspection and
construction of track, maintenance of bridges, repair of signal and communication
systems, repair of RMM
True or false. Fouling a track can apply to both people and machinery -
CORRECT ANSWER-True
Within what distance to the track is a roadway worker considered fouling it? -
CORRECT ANSWER-4 feet from the nearest running rail
a what authorizes movements on controlled track. - CORRECT
ANSWER-Operator/Dispatcher
The RWIC is required to be qualified on physical characteristics when their group
is working on.... - CORRECT ANSWER-All tracks
The EIC is an employee who is in charge of.... - CORRECT ANSWER-A work
group
The main role of the RWIC is.... - CORRECT ANSWER-To establish on track
safety
, When can personal electronic devices be used while on duty? - CORRECT
ANSWER-If there is an emergency at the job site and no other forms of
communication are available
Prior to performing any task that requires fouling a track or has the potential to
foul a track, all roadway workers must participate in an.... - CORRECT
ANSWER-on-track safety briefing
The safety briefing must be conducted.... - CORRECT ANSWER-At the job
location
Whistle boards are required when.... - CORRECT ANSWER-5 or more
employees are working for more than 1 hour
When using foul time with off-track equipment for more than 5 minutes on a main
track you must use.... - CORRECT ANSWER-a supplemental shunting device
Local control is used for.... - CORRECT ANSWER-C&S inspections/testing or
joint C&S and MW switch inspection
How is a job briefing documented? - CORRECT ANSWER-NRPC 4104
When is an on-track safety briefing required? - CORRECT ANSWER-When
performing any task that has potential to foul a track.
Who is responsible for establishing on-track safety? - CORRECT
ANSWER-RWIC
What does foul time ensure for the crew working in the designated area(working
limits)? - CORRECT ANSWER-That no trains will operate within the working
limits
What information is provide by the RWIC when requesting foul time? -
CORRECT ANSWER-Name and title, time limits, track designation, track limits
When is the use of an SSD required? - CORRECT ANSWER-Any situation in
which equipment is used for foul time longer than 5 minutes
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller stephanvdb04. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $11.49. You're not tied to anything after your purchase.