PMP Exam - Process Part 4 Questions with correct answers 2024
- Course
- Institution
Which Kanban key performance indicator allows teams to make reliable commitments about how long it takes them to deliver work? A. Defects B. Cycle time C. WIP D. Velocity - ANSWER-B. Cycle time Explanation : Cycle time is the amount of time it takes for a team to complete a task ...