100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
LSU CM 4100 CONSTRUCTION SCHEDULING AND CONTROL QUIZ 3 actual questions and answers Louisiana State University $12.49   Add to cart

Exam (elaborations)

LSU CM 4100 CONSTRUCTION SCHEDULING AND CONTROL QUIZ 3 actual questions and answers Louisiana State University

1 review
 34 views  1 purchase
  • Course
  • CM 4100 CONSTRUCTION SCHEDULING AND CONTROL
  • Institution
  • CM 4100 CONSTRUCTION SCHEDULING AND CONTROL

LSU CM 4100 CONSTRUCTION SCHEDULING AND CONTROL QUIZ 3 actual questions and answers Louisiana State University

Preview 4 out of 36  pages

  • June 10, 2024
  • 36
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
  • CM 4100 CONSTRUCTION SCHEDULING AND CONTROL
  • CM 4100 CONSTRUCTION SCHEDULING AND CONTROL

1  review

review-writer-avatar

By: lmlang • 3 months ago

avatar-seller
smartzone
Question 1
Correct
1.00 points out of 1.00In resource allocation problems,
Select one:
a.The duration of a project is fixed, but resources are unlimited.
b.Resources are limited, but the duration of a project can be extended.
c.None of the items listed.
Your answer is correct.
The correct answer is: Resources are limited, but the duration of a project can be extended.
Question 2
Correct
1.00 points out of 1.00True or False: After resource allocation, a project's duration may be extended.
Select one:
True
Fals
e
The correct answer is 'True'.
Question 3
Correct
1.00 points out of 1.00In resource allocation problems, the project duration is often .
Select one:
a.Changed
b.Unchanged
Your answer is correct.
The correct answer is: ChangedCM 4100 CONSTRUCTION SCHEDULING AND CONTROL QUIZ 3 actual questions and answers 2024-2025
Louisiana State University The purpose of resource leveling is to
Select one:
Double up resource use in order to accelerate a project.
Smooth the use of resources.
Reduce resource use.
Your answer is correct.
The correct answer is: Smooth the use of resources.Question 4 Solve the resource scheduling problem with the series method. The resource limits are as follows (Chapter 6 Problem 2, page 96): 4C and 3L. After finish resource allocation, choose the correct answer. Please reference the diagram for questions 5-17 (Day 1 through Day 22)
\
DayActivity Resource Use
C L
Day 1
Day 2 to 3
Day 4
Day 5
Day 6
Day 7
Day 8
Day 9 to 12
Day 13 to14
Day 15
Day 16 to 17
Day 18 to 23
Day 24
First, fill out the chart for day 1.
DayActivity Resource Use
C L
Day 1
Select one:
a.
DayActivity Resource Use
C L
Day 1A 0 0
b.
DayActivity Resource Use
C L
Day 1B 1 0Question 5
Correct
1.00 points out of 1.00 c.
The correct answer is:DayActivity Resource Use
C L
Day 1C1 1
DayActivity Resource Use
C L
Day 1A 0 0

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller smartzone. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78075 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.49  1x  sold
  • (1)
  Add to cart