100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
Bus 190 Exam Study $16.39   Add to cart

Exam (elaborations)

Bus 190 Exam Study

 1 view  0 purchase
  • Course
  • Institution

Exam of 7 pages for the course Bus 190 at Bus 190 (Bus 190 Exam Study)

Preview 2 out of 7  pages

  • November 17, 2023
  • 7
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
Bus 190 Exam Study

Pert stands for = project evaluation and review technique

1) which of the following is NOT a property of all LP problems = a computer program (not sure)
This is correct.

2) a feasible solution to a LP problem = must satisfy all of the problem’s constraints
simultaneously

6) If goal was to construct network where all points are connected & distance between them are
short as possible = Minimal-spanning tree.

7) A line in a network that may represent a path or route is called a = arc

9) Transportation models can be used for which decisions = facility location

10) when using general LP model for transportation problem, if 4 sources and 3 destinations =
There are typically 12 decision variables and 7 constraints

12) what is said to exist when total demand equals total supply in a transportation problem = a
balanced problem

13) the minimal-spanning technique would be best used = to determine powerline
communication network wiring within a building.

14) the shortest-route technique would be best used to = determine the path for a truck going
from origin to destination

16) the critical path of a network is the = Longest time path through the network.

17) in a PERT network, the earliest (activity) start time is the =
The earliest time that an activity can start without violation or precedence requirement .

18) the expected time in PERT =The weighted average of the most optimistic time, most
pessimistic time and four times the most likely time.

19) The critical path of a network is the = Path with zero slack or Longest time path through
the network.
(This was on that post by Tommy yesterday. And it is on there twice with different answers.)

20) In a pert network, the latest (activity) start time is the= latest time that an activity can
be started without delaying the entire project.

22) CPM stands for = critical path method

, Bus 190 Exam Study

23) random variable is a variable with values that are = based on probability distribution

24) when a project management network has multiple critical paths, reducing project completion
time by 1 unit = all critical paths

25) The best period of time to crash a project is when the benefit = Exceeds the cost the most

27) in project crashing, the following may happen = a non-critical activity becomes critical

28) value of the dual variable associated w/ constraint in LP solution is the change in = the
objective function from a unit increase in the limit of the constraint

29) the reason that the normal distribution is so prevalent is due to = the Central Limit
Theorem

30) when many independent probability distributions are summed together, which of following
statement is incorrect = The standard deviation of the sum equals to the sum of the
standard deviations.

31) When multiple activities go into finish, the latest finishing time for all activities = largest of
earliest finishing times

32) for the set of 10 normalized weights, which of the following is incorrect = the sum of the
weights equals 10.

*I see another question number 31. SO i put it below here
31) An investor wants to invest up to $100,000 as follows:
X amount into a Certificate of Deposit (CD) that yields an expected annual return of 1% with a
risk index of 2,
Y amount into a Bond with an expected annual return of 3% and a risk index of 4,
Z amounts into a Stock with an expected annual return of 5% and a risk index of 8.
The investors objective is to maximize the total expected annual return of the investment.
However, to be prudent, the investor requires that:
The fraction of the total investment in X must be at least 30%.
The fraction of the total investment in Y must be at least 40% but not exceed 60%.
The fraction of the total investment in Z must not exceed 70%.
The combined portfolio risk index must not exceed 5.

31a) Formulate this investment problem as a linear program by using decimal point numbers for
percentages of return & dollars for the investment amount.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller scaveromulo1. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $16.39. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

77254 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$16.39
  • (0)
  Add to cart