The purpose of Construction Quality Management is to: - Answer- Achieve the quality established by properly developed requirements through the combined responsibility, but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ...
The purpose of Construction Quality Management is to: - Answer- Achieve the quality
established by properly developed requirements through the combined responsibility,
but seperate efforts of contractpr smd government personnel.
Construction Quality Management is the performance of tasks, which ensure that
construction is performed. - Answer- According to plans and specifications, on time,
within a defined budget and a safe work environment.
Partnering relationships are based upon: - Answer- Building trust and dedication to
common goals
It is the responsibility of Quality Assurance Personnel to: - Answer- Periodically verify
that the contractors system of control is working effectively.
An effective contractor quality control program will: - Answer- Be an incentive for work to
be done correctly the first time resulting in earlier completion, reduced field overhead
costs, and greater profits.
The success or failure of all contractors is based upon: - Answer- The ability to control
costs, finance work, estimate jobs, schedule the work, and maintain effective quality
control.
Quality Assurance Personnel have the responsibility to: - Answer- Require contractors
to maintain the quality specified in the plans and specifications.
Inspection is: - Answer- The process by which ongoing and completed work is
examined
During the punch-out inspection of a project: - Answer- Quality Assurance Personnel
must assure that the contractor prepares a punch-list and makes corrections.
If there is a disagreement whether the contractors work complies with the contract: -
Answer- The government makes the final determination
Characteristics that describe a definable feature of work include: - Answer- Cross-
referenced listings to the contractors construction schedule that may have more than
one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - Answer- Follow-up phase
The Quality Assurance Plan: - Answer- Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.99. You're not tied to anything after your purchase.