Test bank and Solution manual for Project Management The Managerial Process 7th Edition by Erik Larson
PRM3701 Assignment 6 Semester 2 2024 | Due 1 October 2024
Question Bank in line with Project Management The Managerial Process,Larson,7e
All for this textbook (15)
Written for
University of South Africa (Unisa)
Project Management (PRM3701)
All documents for this subject (87)
Seller
Follow
passmatetutorials
Reviews received
Content preview
PASSMATE TUTORIALS passmatetutorials@gmail.com
DISCLAIMER: THIS IS NOT AN OFFICIAL GUIDE FROM UNISA. THE FRAMEWORK
IS NOT PREPARED NOR APPROVED BY UNISA, RATHER REPRESENTS A
POSSIBLE SOLUTION TO THE TASK CONSISTENT WITH THEORY. THIS
FRAMEWORK IS ONLY INTENDED TO ASSIST STUDENTS IN GETTING STARTED
WITH THEIR ASSIGNMENT, AND IN NO CASE THIS DOCUMENT SHOULD BE USED
FOR CHEATING, THUS NO STUDENT IS ENCOURAGED TO COPY THIS
DOCUMENT, NOR ITS SECTIONS FOR SUBMISSION. WE BELIEVE THE
FRAMEWORK WILL BE A GOOD STARTING POINT AS IT WAS PREPARED BY OUR
TEAM OF PROFESSIONAL PRIVATE TUTORS WHO ARE EXPERTS IN THE FIELD,
AND IT WAS PREPARED USING VARIOUS SOURCES. ANY SIMILARITY WITH ANY
EXISTING THEORY OR DISCUSSION BY OTHER AUTHORS IS EXCUSED. THE
AUTHORS HOWEVER DO NOT CLAIM MONOPOLY TO KNOWLEDGE HENCE
MODIFICATION OF THE ANSWERS CONTAINED IN THIS FRAMEWORK MAY NOT
BE PROHIBITED AS IT CONTRIBUTES TO EXPANSION OF KNOWLEDGE. FOR ANY
FURTHER GUIDELINE ABOUT THE INFORMATION CONTAINED HERE AND THE
MODULE IN GENERAL, CONTACT PASSMATE TUTORIALS.
Question text
Consider the following table of activities that describes a project network. Without causing
the critical path to become noncritical or otherwise wasting money, by how many days
max could you crash this project? Assume you can crash only one activity at a time and
that crashing is necessary regardless of cost. You do not want to crash the critical path(s)
beyond the point where it (they) is no longer critical as this will not reduce project duration.
Normal Crash
ActivityPredecessorsdurationdurationNormal costCrash cost
(days) (days)
A -- 10 5 R 1,000 R 3,000
B A 20 10 R 4,000 R 6,000
C A 5 4 R 2,000 R 4,000
D B, C 3 2 R 1,000 R 2,000
E B, C 20 10 R 5,000 R 10,000
F B, C 4 3 R 3,000 R 4,000
G D, E, F 10 5 R 2,000 R 5,000
a. From 60 days to 50 days
b. From 60 days to 40 days
c. From 60 days to 30 days
d. From 60 days to 20 days
e. From 60 days to 10 days
Question text
An activity's normal time and cost are 10 and R120, respectively. Its estimated crash time
and cost are 7 and R180, respectively. What is this activity's crash cost per time unit?
a. R20
b. R30
c. R40
d. R50
e. R60
Question text
When crashing a schedule, this may set in when a least-cost method is used.
a. Increased risk
b. Fatigue and resentment
c. Increased cost
d. Decrease in available management reserve
e. Reduced quality
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller passmatetutorials. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $4.53. You're not tied to anything after your purchase.