SAP Certification Practice Exam questions and 100% correct answers
- Course
- Institution
Which of the following control parameters determines the scope of the MRP run in SAP S/4HANA? - Processing key - Purchase requisition - Planned order - Planning mode - Schedule line - correct answer - Processing key What is the highest organizational unit in warehouse management? - War...