Summary of chapter 6 Gower Handbook of Project Management - Agile and Hybrid Project Management
Summary of chapter 7 'measuring performance' from the Gower Handbook of project management
Summary of the chapter 16 'managing cost and earned value' from Gower Handbook of project management
All for this textbook (11)
Written for
Hogeschool Utrecht (HU)
Master projectmanagement
Projectmanagement methoden en standaarden (MPMPMPMMS22_1)
All documents for this subject (16)
Seller
Follow
RSCHO
Reviews received
Content preview
Summary of the hand of project management | Remco van der Schoot
Multitasking Doesn’t support multitasking Allows multitasking (two activities can be
completed in the same time)
Delays Delays are on non-essential tasks Member can immediately start on such
activities
Real-time Uses real-time monitoring and buffer for The duration for certain task may lengthen
activities each activity to ensure on-time completion when an activity needs extra time
applicability When there are unlimited resources and a When there are limited resources and a fixed
flexible deliverable deliverable
Additional sources: Critical Chain vs Critical Path (CCPM vs CPM) | Wrike Guide, Critical Path Method vs
Critical Chain Method for PMP Exam - Updated PMP, PMI-ACP & ITIL Exam Tips 2022 (edward-designer.com)
& 5 Advantages of Critical Chain vs Critical Path (pm-training.net)
2.5. HOOFDSTUK 18 – MANAGING RISK (P.281-305)
2.5.1. RISK CONCEPTS
Managing risk in projects includes all sources of uncertainty, can be both positive and/or negative and can also
exists at the overall project level. The two levels of risks include:
1. Risks in the project:
o Risk events/individual risk = a specific discrete thing that might or might not happen in the
future, but which if they did happen would have a significant effect on achievement of one or
more project objectives.
2. Risk of the project (two definitions):
o Project risk = the exposure of stakeholders to the consequences of variations in the outcome
o Overall project risk = the effect of uncertainty on the project as a whole
The project manager is required to manage:
- Individual risk/risk events -> identifying, assessing and managing individual risk
- (overall) project risk -> account to the project sponsor, project owner and other stakeholders overall
project risk
How to manage both type of risks:
▪ Overall project risk should be addressed as soon as the
pre-project or concept phase, when the scope and
objectives are clarified and agreed upon.
o Risk-reward balance should be agreed upon
through decisions about structure, scope,
content and context of the project
▪ When the project is initiated traditional project risk
process can be used to address explicitly the individual risks that lie within the project.
▪ At key points in the project it will be necessary to revisit the assessment of overall project risk
P a g i n a 25 | 35
, Summary of the hand of project management | Remco van der Schoot
2.5.2. INTRODUCING THE RISK PROCESS
Informal step Formal process Purpose
Getting started [what are Risk process To define the scope, objections, and practical parameters of
we trying to achieve?] initiation the project risk management process
Finding risks [what could Risk To identify all currently knowable risks, including both
affect us achieving this?] identification individual risks and sources of overall project risk
Setting priorities [Which of Qualitative Risk To evaluate key characteristics of individual risks enabling
those things are most Assessment them to be prioritized for further action, and recognizing
important?] patterns of risk exposure
Quantitative To evaluate the combined effect of risks on the project
Risk Analysis outcome and assess overall project risk exposure
Deciding what to do [What Risk Response To determine appropriate response strategies and actions
shall we do about them?] Planning for each individual risk and for overall project risk
Acting [Did we do what we Risk Response To implement agreed actions, determine whether they are
said we would do?] Implementation working and identify any resultant secondary risks
Telling others [Who needs Risk To inform project stakeholders about the current level of
to know?] communication risk exposure and its implications for project success,
including both individual risks and overall project risk, as
appropriate
Keeping up to date [What Risk Review To review changes in identified risks and overall project risk
has changed and what exposure, identify additional actions as required and assess
should we do now?] the effectiveness of the project risk management process
Capturing lessons [What Post-Project To identify risk-related lessons to be learned for future
did we learn?] Review projects
P a g i n a 26 | 35
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller RSCHO. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $3.81. You're not tied to anything after your purchase.