100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PK0-004 Project+ BEST STUDY GUIDE 2021/2022 $10.99   Add to cart

Exam (elaborations)

PK0-004 Project+ BEST STUDY GUIDE 2021/2022

 3 views  0 purchase
  • Course
  • Institution

PK0-004 Project+ BEST STUDY GUIDE 2021/2022

Preview 4 out of 155  pages

  • July 22, 2022
  • 155
  • 2021/2022
  • Exam (elaborations)
  • Questions & answers
avatar-seller
PK0-004 Project+ BEST STUDY GUIDE
2021/2022

A milestone task on the critical path has been completed.

which of the following should the project manager notify?

A owner of predecessor task
B project team
C project sponsor
D project steering committee correct answer- C

During a project assessment, a project manager determines the initial project cost
estimates were incorrect oh, and there is not enough budget left, including reserves, to
complete the project.

Which of the following actions should the project manager take?

A alert the project sponsor of the situation
B contact the customer and request more funding
C announce the project will end due to lack of funds
D attempt to save money in downstream activities correct answer- A

Which of the following is the primary purpose of an MOA or an mou?

A State expectations of all signatory parties to reduce potential misunderstandings

B facilitate potential legal action and resulting remediation if one of the signatory parties
violate any terms

C enumerate a detail code of conduct for all employees, contractors, and
subcontractors participating in the program.

D provide transparency to competitors regarding all signatory parties correct answer- A

two team members have concluded that documentation is not required due to the size
of the current project. The project manager has encouraged them to align strictly with
the process.

which of the following conflict resolution techniques has the project manager utilized?

,A smoothing
B forcing
C compromising
D avoiding correct answer- B

The client accepts the critical design review.

which of the following meetings should be held to move to the next step in the project?

A execution
B kickoff
C closure
D planning correct answer- B

A project manager is working on the project charter.

Which of the following phases does this describe?

A initiation
B planning
C execution
D closing correct answer- A

A project in the execution phase is over budget, and tasks on the critical path are on
schedule.

Which of the following should the project manager do next?

A update the project management plan
B issue a change request
C revise the project charter
D evaluate the impact to the baseline correct answer- D

Several team members report that meeting objectives are not being met.

which of the following documents would a project manager free to make team meetings
more effective? Choose two

1 create an s o w prior to each meeting and adhere to it
2 create a meeting agenda prior to each meeting and adhere to it
3 create a lessons learned list prior to each meeting and adhere to it
4 create a project charter prior to each meeting and adhere to it
5 create an action item list during the meeting and adhere to it
6 create a corrective action plan prior to each meeting and adhere to it
7 create a WBS prior to each meeting and adhere to it

,A 2,5
B 1,4 correct answer- A

Which of the following documents should be used prior to high-level recording to key
stakeholders?

A dashboard
B communication plan
C statement of work
D project charter correct answer- A

A new project charter is being drafted.

which of the following would be the best source for the high-level project requirements?

A sponsor
B project manager
C project management office
D project team correct answer- A

Which of the following project document should be used to record the occurrence of an
unplanned event?

A action log
B risk log
C change log
D issue log correct answer- D

Which of the following documents does offender rely most before committing funding
and resources to a project?

A SOW
B PO
C SLA
D MOU correct answer- A

which of the following measurements would give the project manager the best estimate
of the total cost of an active project?

A EAC
B BAC
C TCPI
D ETC correct answer- A

A customer will have ongoing changes to project requirements.

, which of the following is the best project management methodology for this
requirement?

A waterfall
B agile
C PRINCE2
D BOTTOM UP correct answer- B

Which of the following describes risk mitigation?

A the transfer of the risk to another entity or project inside or outside the organization,
along with the associated costs.

B the understanding of the risks with a detailed explanation and how to project intends
to address the potential for occurrence.

C the quantification of the risk in terms of how much the risk of potentially cost the
project or parent organization.

D The waiting or privatization of the risk against all of their identified risks within this
project or others associated with it. correct answer- B

Which of the following is a definition of an RFP?

A a document sent to potential vendors to solicit a bid for a project.

B a document sent a potential vendors to request information for skills and experience
for a project.

C a document sent to potential vendors to request a commitment for a project.

D a document cents potential vendors to solicit information that excludes pricing
information for a project. correct answer- A

A customer has requested additional features for an active project.

which of the following steps should take place next?

A implement the requested changes
B evaluate the impact of the changes
C update all project documents
D submit the requested changes to the CCB correct answer- B

A project manager has an opportunity to add highly skilled expert to the team who can
increase the probability of the project success.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller YANCHY. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $10.99. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75323 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$10.99
  • (0)
  Add to cart