[Show more]ASTM C1064 - Answer-Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement 
Concrete 
The end of the temperature sensing portion of the temperature measuring device shall be submerged a 
minimum of ____ into the freshly mixed concrete. - Answer-3 inches [75 mm] 
C1064, Sec. 8.1 
The ...
Preview 3 out of 29 pages
Add to cartASTM C1064 - Answer-Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement 
Concrete 
The end of the temperature sensing portion of the temperature measuring device shall be submerged a 
minimum of ____ into the freshly mixed concrete. - Answer-3 inches [75 mm] 
C1064, Sec. 8.1 
The ...
Section 1: Temperature of Freshly Mixed Hydraulic-Cement Concrete - C1064 
The end of the temperature sensing portion of the temperature measuring device is submerged a 
minimum of _____ into the freshly mixed concrete. - 3 inches 
The temperature measuring device shall be capable of accurately meas...
Preview 2 out of 14 pages
Add to cartSection 1: Temperature of Freshly Mixed Hydraulic-Cement Concrete - C1064 
The end of the temperature sensing portion of the temperature measuring device is submerged a 
minimum of _____ into the freshly mixed concrete. - 3 inches 
The temperature measuring device shall be capable of accurately meas...
For concrete with aggregates less than 3 inches, the thermometer must remain in the fresh concrete 
sample a minimum of 5 minutes or until the temperature reading stabilizes. (True or False) - AnswerFalse 
The temperature measuring device must be accurate to within 0.1 degrees. (True or False) - Ans...
Preview 2 out of 9 pages
Add to cartFor concrete with aggregates less than 3 inches, the thermometer must remain in the fresh concrete 
sample a minimum of 5 minutes or until the temperature reading stabilizes. (True or False) - AnswerFalse 
The temperature measuring device must be accurate to within 0.1 degrees. (True or False) - Ans...
Following are three of the four purposes for which aggregates are sampled; supply the fourth. 
Aggregates are sampled: 
a) for the acceptance or rejection of materials. 
b) for the control of operations at the site of use. 
c) for preliminary investigation of the potential source of supply. 
d) ____...
Preview 1 out of 2 pages
Add to cartFollowing are three of the four purposes for which aggregates are sampled; supply the fourth. 
Aggregates are sampled: 
a) for the acceptance or rejection of materials. 
b) for the control of operations at the site of use. 
c) for preliminary investigation of the potential source of supply. 
d) ____...
For concrete with aggregates less than 3 inches, the thermometer must remain in the fresh concrete 
sample a minimum of 5 minutes or until the temperature reading stabilizes. (T or F) - Answer-False (2-5 
minutes) 
The temperature measuring device must be accurate to within 0.1 degree. (T or F) - An...
Preview 2 out of 10 pages
Add to cartFor concrete with aggregates less than 3 inches, the thermometer must remain in the fresh concrete 
sample a minimum of 5 minutes or until the temperature reading stabilizes. (T or F) - Answer-False (2-5 
minutes) 
The temperature measuring device must be accurate to within 0.1 degree. (T or F) - An...
1. Which of the following statements is false? Aggregates are sampled: 
A. For the acceptance or rejection of materials 
B. For the control of operations at the site of use 
C. For preliminary investigation of the potential source of supply 
D. For the control of the product at the source of supply ...
Preview 1 out of 4 pages
Add to cart1. Which of the following statements is false? Aggregates are sampled: 
A. For the acceptance or rejection of materials 
B. For the control of operations at the site of use 
C. For preliminary investigation of the potential source of supply 
D. For the control of the product at the source of supply ...
These procedures for capping enable concrete cylinders and cores to meet the standard's requirements 
for ________ and _________. - Answer-Planeness, perpendicularity 
Equipment needed for the capping process includes capping _____ , _____devices, and ______ pots. - 
Answer-Plates, alignment, melti...
Preview 2 out of 9 pages
Add to cartThese procedures for capping enable concrete cylinders and cores to meet the standard's requirements 
for ________ and _________. - Answer-Planeness, perpendicularity 
Equipment needed for the capping process includes capping _____ , _____devices, and ______ pots. - 
Answer-Plates, alignment, melti...
Q1. Start molding specimens for strength tests within 30 minutes after fabricating the composite sample. 
A. True 
B. False - B. False 
ASTM C172 -Para (4.1.2) - Start molding. 
specimens for strength tests within 15 min after fabricating the 
composite sample. 
Q2. The maximum allowable time betwee...
Preview 4 out of 43 pages
Add to cartQ1. Start molding specimens for strength tests within 30 minutes after fabricating the composite sample. 
A. True 
B. False - B. False 
ASTM C172 -Para (4.1.2) - Start molding. 
specimens for strength tests within 15 min after fabricating the 
composite sample. 
Q2. The maximum allowable time betwee...
ASTM C31 / C31M-06 - Standard Practice for Making, Curing, Protecting & Transporting Test 
Specimens in the Field Conditions. 
ASTM C1064 /C1064M-05 - Standard Test Method for Temperature of Freshly Mixed HydraulicCement Concrete 
ASTM C172 -07 - Standard Practice For Sampling Freshly Mixed Concrete...
Preview 2 out of 9 pages
Add to cartASTM C31 / C31M-06 - Standard Practice for Making, Curing, Protecting & Transporting Test 
Specimens in the Field Conditions. 
ASTM C1064 /C1064M-05 - Standard Test Method for Temperature of Freshly Mixed HydraulicCement Concrete 
ASTM C172 -07 - Standard Practice For Sampling Freshly Mixed Concrete...
The method of determining air content of concrete containing lightweight aggregate is the pressure 
method - False. Relatively dense 
Is the following statement true or false? When making a test cylinder from concrete being used in 
construction, the field technician must also measure the slump of t...
Preview 1 out of 2 pages
Add to cartThe method of determining air content of concrete containing lightweight aggregate is the pressure 
method - False. Relatively dense 
Is the following statement true or false? When making a test cylinder from concrete being used in 
construction, the field technician must also measure the slump of t...
The sensor of the temperature measureing device shall be submerged a minimum of ____ in - Answer-3 
(75mm) 
The temperature measureing device shall have a capacity of measuring temperature of freshly mixed 
conrcrete to +-_____ degrees F throught a range of _____ - Answer-1(.5 degrees C), 30-120 (0-...
Preview 2 out of 12 pages
Add to cartThe sensor of the temperature measureing device shall be submerged a minimum of ____ in - Answer-3 
(75mm) 
The temperature measureing device shall have a capacity of measuring temperature of freshly mixed 
conrcrete to +-_____ degrees F throught a range of _____ - Answer-1(.5 degrees C), 30-120 (0-...
ASTM C1064 - Answer-Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement 
Concrete 
The sensor of the temperature measuring device shall be submerged a minimum of ______ inches into 
the freshly mixed concrete. - Answer-3" 
The temperature measuring device shall have a capacity of...
Preview 3 out of 16 pages
Add to cartASTM C1064 - Answer-Standard Test Method For Temperature of Freshly Mixed Hydraulic-Cement 
Concrete 
The sensor of the temperature measuring device shall be submerged a minimum of ______ inches into 
the freshly mixed concrete. - Answer-3" 
The temperature measuring device shall have a capacity of...
The total time allowed between obtaining the first and final portions of a composite sample is - Answer- 
15 minutes 
When it is necessary to wet sieve the concrete sample, wet sieving should be performed after the 
individual samples are remixed into a composite sample (T or F) - Answer-F 
Tests fo...
Preview 2 out of 8 pages
Add to cartThe total time allowed between obtaining the first and final portions of a composite sample is - Answer- 
15 minutes 
When it is necessary to wet sieve the concrete sample, wet sieving should be performed after the 
individual samples are remixed into a composite sample (T or F) - Answer-F 
Tests fo...
The sensor of the temperature measuring device shall be submerged a minimum of _____ in. 
[_____mm] into the freshly mixed concrete. - Answer-3 in. [75 mm] 
The temperature measuring device shall have a capacity of measuring temperature of freshly mixed 
concrete to +- _____ degrees F [+- _____ C] t...
Preview 2 out of 14 pages
Add to cartThe sensor of the temperature measuring device shall be submerged a minimum of _____ in. 
[_____mm] into the freshly mixed concrete. - Answer-3 in. [75 mm] 
The temperature measuring device shall have a capacity of measuring temperature of freshly mixed 
concrete to +- _____ degrees F [+- _____ C] t...
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Stuvia is a marketplace, so you are not buying this document from us, but from seller ACADEMICMATERIALS. Stuvia facilitates payment to the seller.
No, you only buy these notes for $18.99. You're not tied to anything after your purchase.
4.6 stars on Google & Trustpilot (+1000 reviews)
78252 documents were sold in the last 30 days
Founded in 2010, the go-to place to buy study notes for 14 years now