[Show more]Actual Cost - ANSWER The realized cost incurred for the work performed on an activity during 
a specific time period 
Organizational Breakdown Structure - ANSWER A hierarchical representation of the project 
organization, which illustrates the relationship between project activities and the organiza...
Preview 4 out of 51 pages
Add to cartActual Cost - ANSWER The realized cost incurred for the work performed on an activity during 
a specific time period 
Organizational Breakdown Structure - ANSWER A hierarchical representation of the project 
organization, which illustrates the relationship between project activities and the organiza...
During the initiating stage, which of the following elements will be identified to meet the 
project goals? 
A) Key deliverables 
A car manufacturing company conceptualized a new car that will be more fuel efficient, 
ergonomically designed, and that satisfies the latest safety regulations. This car...
Preview 4 out of 54 pages
Add to cartDuring the initiating stage, which of the following elements will be identified to meet the 
project goals? 
A) Key deliverables 
A car manufacturing company conceptualized a new car that will be more fuel efficient, 
ergonomically designed, and that satisfies the latest safety regulations. This car...
________ is typically not referred to as a buffer type in critical chain project management. 
A. Resource buffer 
B. Free buffer 
C. Feeding buffer 
D. Project buffer - Answer B. Free buffer 
An accepted deadline for a project approaches. However, the project manager 
realizes only 75% percent of th...
Preview 4 out of 68 pages
Add to cart________ is typically not referred to as a buffer type in critical chain project management. 
A. Resource buffer 
B. Free buffer 
C. Feeding buffer 
D. Project buffer - Answer B. Free buffer 
An accepted deadline for a project approaches. However, the project manager 
realizes only 75% percent of th...
During which of the following project development life cycles are the project scope, schedule 
and budget determined in the early phases of the life cycle? - Answer Predictive Life Cycle 
Which of the following is the correct definition of a project management methodology? - Answer 
System of practi...
Preview 4 out of 31 pages
Add to cartDuring which of the following project development life cycles are the project scope, schedule 
and budget determined in the early phases of the life cycle? - Answer Predictive Life Cycle 
Which of the following is the correct definition of a project management methodology? - Answer 
System of practi...
1. The successful project managers spend most of their time: 
A) Planning with their personnel. B) Planning with top management C) 
Communicating with project team D) Studying project results. 
2. Of the following types of contracts - which has the HIGHEST risk for the seller ? A. 
Cost plus fixed f...
Preview 2 out of 9 pages
Add to cart1. The successful project managers spend most of their time: 
A) Planning with their personnel. B) Planning with top management C) 
Communicating with project team D) Studying project results. 
2. Of the following types of contracts - which has the HIGHEST risk for the seller ? A. 
Cost plus fixed f...
Question No : 1 
While managing a project, you decide to create a prototype of your product first to ensure that it is acceptable to 
stakeholders before creating your product. This is an example of: 
Choice 1 Risk mitigation 
Choice 2 Risk avoidance 
Choice 3 Simulation 
Choice 4 Project assumption...
Preview 4 out of 316 pages
Add to cartQuestion No : 1 
While managing a project, you decide to create a prototype of your product first to ensure that it is acceptable to 
stakeholders before creating your product. This is an example of: 
Choice 1 Risk mitigation 
Choice 2 Risk avoidance 
Choice 3 Simulation 
Choice 4 Project assumption...
Question No : 3 
Your customer wants some change to be effected in the project scope. You determine that the change in scope will not impact the 
project schedules but will cost the project an additional $50,000. What should you do FIRST? 
Choice 1 Try crashing or fast tracking the project. 
Choice ...
Preview 4 out of 386 pages
Add to cartQuestion No : 3 
Your customer wants some change to be effected in the project scope. You determine that the change in scope will not impact the 
project schedules but will cost the project an additional $50,000. What should you do FIRST? 
Choice 1 Try crashing or fast tracking the project. 
Choice ...
Question No : 1 
Which of the following is NOT a characteristic of a project? 
Choice 1 Constrained by limited resources 
Choice 2 Planned, executed, and controlled 
Choice 3 Creates a unique product or service 
Choice 4 Ongoing and repetitive 
Correct Choice :
Preview 4 out of 342 pages
Add to cartQuestion No : 1 
Which of the following is NOT a characteristic of a project? 
Choice 1 Constrained by limited resources 
Choice 2 Planned, executed, and controlled 
Choice 3 Creates a unique product or service 
Choice 4 Ongoing and repetitive 
Correct Choice :
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Stuvia is a marketplace, so you are not buying this document from us, but from seller Examsplug. Stuvia facilitates payment to the seller.
No, you only buy these notes for $35.49. You're not tied to anything after your purchase.
4.6 stars on Google & Trustpilot (+1000 reviews)
75323 documents were sold in the last 30 days
Founded in 2010, the go-to place to buy study notes for 14 years now