[Show more]A project estimator is developing a cost estimate for construction of a new diagnostic imaging wing. The projected costs are: 
 
Fixed equipment installation charges $700,000 
 
Site isolation $50,000 
 
Annual utilities $425,000 
 
Construction materials $1,200,000 
 
Portable equipment $900,000 
...
Preview 3 out of 19 pages
Add to cartA project estimator is developing a cost estimate for construction of a new diagnostic imaging wing. The projected costs are: 
 
Fixed equipment installation charges $700,000 
 
Site isolation $50,000 
 
Annual utilities $425,000 
 
Construction materials $1,200,000 
 
Portable equipment $900,000 
...
1. What NFPA code is specific to healthcare and establishes criteria for levels of health care services or systems based on risk to the patients, staff, or visitors in health care facilities to minimize the hazards of fire, explosion, and electricity? Correct Answer-NFPA 99-2012 
 
What NFPA code de...
Preview 1 out of 4 pages
Add to cart1. What NFPA code is specific to healthcare and establishes criteria for levels of health care services or systems based on risk to the patients, staff, or visitors in health care facilities to minimize the hazards of fire, explosion, and electricity? Correct Answer-NFPA 99-2012 
 
What NFPA code de...
What are the requirements for a new patient room door for a healthcare occupancy? Correct Answer-45.5 inches wide & smoke tight 
 
What are the typical contractor responsibilities during healthcare construction? Correct Answer-Operations manuals 
Maintenance Manuals 
Punch list 
TAB Reports 
Medical...
Preview 2 out of 13 pages
Add to cartWhat are the requirements for a new patient room door for a healthcare occupancy? Correct Answer-45.5 inches wide & smoke tight 
 
What are the typical contractor responsibilities during healthcare construction? Correct Answer-Operations manuals 
Maintenance Manuals 
Punch list 
TAB Reports 
Medical...
What does the acronym FTE stand for? Correct Answer-Full Time Equivalent 
 
What are the number of hours that make up an FTE? Correct Answer-40 hours per week; 2080 hours per year 
 
40 hours per week x 52 weeks = 2,080 hours 
 
What are budgeted hours? Correct Answer-Budgeted hours are estimated ho...
Preview 2 out of 10 pages
Add to cartWhat does the acronym FTE stand for? Correct Answer-Full Time Equivalent 
 
What are the number of hours that make up an FTE? Correct Answer-40 hours per week; 2080 hours per year 
 
40 hours per week x 52 weeks = 2,080 hours 
 
What are budgeted hours? Correct Answer-Budgeted hours are estimated ho...
Certified Healthcare Facility Manager questions with correct answers
Preview 1 out of 2 pages
Add to cartCertified Healthcare Facility Manager questions with correct answers
Define blueprint, CADD, plan view, elevation view. Correct Answer-Blueprint - A drawing or series of drawings that show the layout of a building, room, plot of land, or the construction of an object. Building blueprints use specific symbols to indicate features such as doors, windows, and electrical...
Preview 2 out of 14 pages
Add to cartDefine blueprint, CADD, plan view, elevation view. Correct Answer-Blueprint - A drawing or series of drawings that show the layout of a building, room, plot of land, or the construction of an object. Building blueprints use specific symbols to indicate features such as doors, windows, and electrical...
Fire protection for a new construction sleeping suite not exceeding 7500 sqft Correct Answer-The room must have a sprinkler system and complete smoke detection OR sprinkler system with QRS or residential sprinklers 
 
Fire protection for a new construction sleeping suite greater than 7500 sqft Corre...
Preview 4 out of 109 pages
Add to cartFire protection for a new construction sleeping suite not exceeding 7500 sqft Correct Answer-The room must have a sprinkler system and complete smoke detection OR sprinkler system with QRS or residential sprinklers 
 
Fire protection for a new construction sleeping suite greater than 7500 sqft Corre...
Where do you find the most important design codes and standards information for your project? Correct Answer-• FGI Guidelines - 2014 version 
• NFPA 99 - 2012 version 
• NFPA 101® - 2012 version 
• State Department of Health Licensing Regulation 
• State Fire Marshal - local code AHJ ...
Preview 3 out of 19 pages
Add to cartWhere do you find the most important design codes and standards information for your project? Correct Answer-• FGI Guidelines - 2014 version 
• NFPA 99 - 2012 version 
• NFPA 101® - 2012 version 
• State Department of Health Licensing Regulation 
• State Fire Marshal - local code AHJ ...
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Stuvia is a marketplace, so you are not buying this document from us, but from seller cracker. Stuvia facilitates payment to the seller.
No, you only buy these notes for $35.99. You're not tied to anything after your purchase.
4.6 stars on Google & Trustpilot (+1000 reviews)
77254 documents were sold in the last 30 days
Founded in 2010, the go-to place to buy study notes for 14 years now