100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
OSCM 373- Exam 2 WITH Q & A $18.49   Add to cart

Exam (elaborations)

OSCM 373- Exam 2 WITH Q & A

 4 views  0 purchase
  • Course
  • OSCM 373-
  • Institution
  • OSCM 373-

OSCM 373- Exam 2 WITH Q & A What is the average Wait-Time? - CORRECT ANSWER 30 minutes Working (uses Little Law's rule): Wq = Lq / λ = 4/8 = 1/2 hour = 30 minutes What effect an increase of Server-Utilization has on expected Wait-Time? - CORRECT ANSWER Expected wait time would increa...

[Show more]

Preview 3 out of 16  pages

  • November 8, 2024
  • 16
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • OSCM 373-
  • OSCM 373-
avatar-seller
janetheuri
What is the function of a work breakdown structure?

- CORRECT ANSWER Provides the basis for detailed time and cost estimates on a
project

When using a computing algorithm to analyze large network diagrams, what are the four
pieces of information needed for each activity?
- CORRECT ANSWER Early start, early finish, late start, and late finish

When using a Gantt chart with a complex project, what tool should be used in
conjunction with the chart?
- CORRECT ANSWER Network diagram

T/F: Early start and finish times involve a forward pass, and late start and finish times
use a backward pass through the network.
- CORRECT ANSWER True

What is a network diagram, which is used by the PERT and CPM project management
techniques? - CORRECT ANSWER Diagram of project activities that shows their
sequential relationships with arrows and nodes

The slack time on the critical path is always what? - CORRECT ANSWER Zero

The critical path in a network diagram is defined as what?
- CORRECT ANSWER The longest path from start to finish which determines the
overall project duration.

If a budget was too optimistic, it was ____________ the actual project cost.
- CORRECT ANSWER lower than

What is used in AOA diagrams to clarify relationships, such as two activities that have
the same starting and ending nodes?
- CORRECT ANSWER Dummy activity

Select all of the reasons why a project manager would want to shorten the duration of a
project.
- CORRECT ANSWER- Incentive payment earned if project completion date is early
- To free up resources to work on another project
- Monetary penalty due if agreed-to schedule is exceeded

All of the following information can be produced by the network diagram computing
algorithm except which?
- CORRECT ANSWER Most expensive path

Select all of the rules project managers follow when crashing a schedule.
- CORRECT ANSWER- Crash the schedule one period at a time

,- Recalculate the critical path after each crashing
- Crash the least expensive activity on the critical path

Which of the following is calculated in a forward pass?
- CORRECT ANSWERE S = 0
ES + Activity time = EF

In critical chain project management the critical path is viewed as a what?
- CORRECT ANSWER Bottleneck

Why is slack time valuable information for project managers?
- CORRECT ANSWER Resources may be shifted to more critical activities away from
those with slack

There are many advantages to using a project management software package. Among
them are which of the following?
- CORRECT ANSWER-It automatically formats reports.
- It can generate various chart types, including basic Gantt charts.
- It enables what-if scenarios.
- It can enhance communication among team members.
- It provides a logical planning structure.
- It imposes a methodology and a common project management terminology.
- It can flag the occurrence of constraint violations.
- It can generate multiple levels of summary reports and detailed reports.

Select all of the reasons that project costs may exceed budgeted amounts.
- CORRECT ANSWER- Weather or supplier delays
- Budget too optimistic
- Rework of substandard workmanship

T/F: It is common for projects to fail, either partially or completely.
- CORRECT ANSWER True

In project management, shortening activity durations by applying additional resources to
it is called ______________.
- CORRECT ANSWER crashing

Which of the following statements about risk probability and cost are true?
- CORRECT ANSWER Probability of occurrence of a risk is highest at the start.

Why are only activities on the critical path candidates for crashing?
- CORRECT ANSWER Only the critical path directly affects the completion date

Similar to the theory of constraints, critical chain project management uses what to
support the critical path?
- CORRECT ANSWER Buffers

, What are some of the features of common project management software?
- CORRECT ANSWER- Track progress/performance of scheduled project activities
- Flag missing precedence relationships between activities
- Assign resources to project activities

Operating in an environment of uncertainty, projects are subject to what negative
outcomes?
- CORRECT ANSWER Delays, budget overruns, inability to meet technical
requirements

T/F: With proper risk management all cost, schedule and technical risks can always be
avoided on a project.
- CORRECT ANSWER False

Customers arrive at a rate (λ) of 8 per hour (arrival pattern can be described with a
Poisson distribution with a mean of 8). Service representative requires an average of 6
minutes (1/μ) to assist a customer (service time can be described with an exponential
distribution with a mean of 6).
What is the average queue length?
- CORRECT ANSWER3.2
Working (uses M/M/1 system):
Arrival Rate λ = 8 customers/hour
1/μ = 6 minutes => Service Rate, μ = 60/6 = 10 customers/hour
Lq= λ^2/(μ *(μ-λ)) = 8^2/(10*(10-8)) = 64/20 = 3.2 customers

Customers arrive at a rate (λ) of 45 per hour (arrival pattern can be described with a
Poisson distribution with a mean of 45). A service representative requires an average of
6 minutes (1/μ) to assist a customer (service time can be described with an exponential
distribution with a mean of 6). The company employs 6 service representatives. What is
the average queue length?
- CORRECT ANSWER1.265 customers
Working (M/M/S system):
λ = 45 customers/hour
1/μ = 6 minutes => μ = 60/6 = 10 customers/hour
Referring to the table with λ/μ = 45/10 = 4.5 & M=6 => Lq = 1.265 customers

Customers arrive to a concession stand at the rate of 72 per hour. Arrival rate can be
described by a Poisson distribution. The stand has 4 windows. Buying a hot dog takes
on average 3 minutes per customer and varies exponentially.
What is the maximum waiting-line length (at least) 40% of the time?
- CORRECT ANSWER2

Customers arrive at a rate (λ) of 8 per hour. Each service representative requires an
average of 6 minutes to assist a customer. The system has an average queue length of
4 customer.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller janetheuri. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $18.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

78075 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$18.49
  • (0)
  Add to cart