100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
PRINCE2 TEST QUESTIONS AND ANSWERS $12.49   Add to cart

Exam (elaborations)

PRINCE2 TEST QUESTIONS AND ANSWERS

 2 views  0 purchase
  • Course
  • PRINCE2
  • Institution
  • PRINCE2

PRINCE2 TEST QUESTIONS AND ANSWERS

Preview 2 out of 13  pages

  • October 21, 2024
  • 13
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • PRINCE2
  • PRINCE2
avatar-seller
GEEKA
PRINCE2 TEST QUESTIONS AND ANSWERS

Which theme establishes mechanisms to determine whether the project is (and
remains) desirable, viable, and achievable? - Answers-Business Case theme

Which type of risk response only reduces the financial impact of a risk? - Answers-
Transfer

What PRINCE2 term is used to describe the adoption of PRINCE2 across an
organization? - Answers-Embedding

What PRINCE2 term is used to describe the measurable improvement resulting from an
outcome that is perceived as positive by one or more stakeholders? - Answers-Benefit

Which role is responsible for demonstrating that benefits have occurred? - Answers-
Senior User

What are the five core activities of configuration management? - Answers-Planning,
identification, control, status accounting, and verification and audit

Which of the PRINCE2 principles ensures that everyone on the project team
understands what is expected of them? - Answers-Defined roles and responsibilities

Which three project interests are represented on the Project Board? - Answers-
Business, user, and supplier

Which PRINCE2 role is ultimately responsible for the project? - Answers-Executive

Which management product documents the justification for undertaking the project? -
Answers-Business Case

What management product describes a project's approach to managing uncertainty? -
Answers-Risk Management Strategy

When a team is sited at a different geographic location from the Project Manager, what
role might be used to manage that team? - Answers-Team Manager

Which term is used to describe anyone who can affect or be affected by the project? -
Answers-Stakeholder

During which process is the Communication Management Strategy created? - Answers-
Initiating a Project

Which theme defines and implements the means by which the project will create and
verify products that are fit for their purpose? - Answers-Quality theme

, Which quality review technique role will review and submit questions about the product
under review? - Answers-Reviewer

Is quality assurance internal or external to the project management team? - Answers-
External

Which of the PRINCE2 principles ensures efficient and economic use of management
time? - Answers-Manage by exception

PRINCE2 consists of four integrated elements: themes, processes, the project
environment, and which other? - Answers-Principles

Which management product is used to determine how and when a measurement of the
achievement of the project's benefits can be made? - Answers-Benefits Review Plan

Which section of the Business Case balances the forecast benefits against the time,
cost, and risk of the project? - Answers-Investment appraisal

During which process is version one of the detailed Business Case created? - Answers-
Initiating a Project

During which process is the Project Brief created? - Answers-Starting up a Project

Which management product contains the customer's quality expectations and
acceptance criteria? - Answers-Project Product Description

Which is always measurable: the customer's quality expectations or acceptance
criteria? - Answers-Acceptance criteria

What does PRINCE2 call evidence that has been gathered to show that quality activities
have been carried out? - Answers-Quality records

During which process is the Project Product Description first created? - Answers-
Starting up a Project

What role is responsible for creating the Project Product Description? - Answers-Project
Manager

Which role is responsible for creating the Quality Register? - Answers-Project Manager

During which process is the Quality Management Strategy created? - Answers-Initiating
a Project

What are the three levels of plan recommended by PRINCE2? - Answers-Project,
stage, and team

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller GEEKA. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

72042 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.49
  • (0)
  Add to cart