100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ARE 5.0 - Construction & Evaluation Test with 100% Correct | Latest Updated Graded A+ $13.24   Add to cart

Exam (elaborations)

ARE 5.0 - Construction & Evaluation Test with 100% Correct | Latest Updated Graded A+

 1 view  0 purchase
  • Course
  • ARE 5.0
  • Institution
  • ARE 5.0

ARE 5.0 - Construction & Evaluation Test with 100% Correct | Latest Updated Graded A+

Preview 4 out of 35  pages

  • October 18, 2024
  • 35
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • ARE 5.0
  • ARE 5.0
avatar-seller
Examsplug
ARE 5.0 - Construction & Evaluation Test
with 100% Correct | Latest Updated Graded
A+

How is "contract time" defined? - ✔✔Starts at date established in the agreement and ends
at Substantial Completion



Which party has sole responsibility for the means and methods of construction? - ✔✔GC




What two parties should each receive a copy of an Architect's field reports? - ✔✔Owner and GC




Name two differences between a Change Order and a Construction Change Directive - ✔✔-
CO must be approved by Owner, Architect, and GC and cost must be agreed upon

- CCD must only be agreed upon by Owner and Architect, without all parties agreeing on cost



Which party produces an RFI? - ✔✔GC, Owner, or Architect



When is the GC allowed to submit a request for payment of a Construction Change Directive to
the Owner on the application for payment? - ✔✔Upon completion of the work and agreement
of the additional cost of work by the Contractor and Owner

,Name 4 types of submittals the GC must make to the Architect - ✔✔- Shop drawings

- Samples

- Product data

- Sustainability documents



Which document is used to record minor changes in the work? - ✔✔G710
Architect's Supplemental Instructions



If the work does not conform with the contract documents, who has the authority to reject
the work? - ✔✔Architect




The Architect's review of shop drawings does not relieve the GC of what? -
✔✔Conformance with the contract documents



During the construction phase, who may make a claim on the project? - ✔✔Owner or GC
may take action if they seek an adjustment to the time or payment of money or other relief
from the terms of the contract



In a shop drawing review, what are the similarities and differences between the "revise and
resubmit" and "rejected" designations assigned by the Architect? - ✔✔Neither submittal
complies with the contract documents as submitted. In the first, the contractor may provide
additional information or make corrections and return the submittal to the Architect for review.
In the second, an item is unsuitable for use in the project and may not be resubmitted to the
Architect for review.

,Describe the difference in roles between a mediator and an arbitrator - ✔✔In mediation, this
person facilitates a discussion for the parties to reach their own settlement. In arbitration, this
person allows the parties to submit their evidence and hears witness testimony before making
a decision or ruling on the matter



Which party pays for additional non-conformance field testing? - ✔✔GC




What information must be included on every progress payment application? - ✔✔- Value of
the work completed to date

- Value of stored material



Who pays for work rejected by the Architect? - ✔✔GC




What fee method should be used when the Owner has identified a specific set of services?
- ✔✔Stipulated sum




If an Owner fails to substantially perform according to contract, what must an Architect do
to terminate the contract? - ✔✔Give the Owner 7 days written notice




When are shop drawings usually prepared? - ✔✔After the subcontractor or material supplier
has signed a contract with the GC

, Mechanic's Lien - ✔✔Claim against a property made by a Contractor, material supplier,
or Architect for unpaid debt of the Owner



What is the advantage to the Owner of using a Construction Change Directive? - ✔✔Gives
the Owner a way to order changes in the work before agreeing to an adjustment to the cost
and/or time



When does the GC's warranty period start? - ✔✔Substantial completion




What post-construction activity is a prerequisite for LEED certification? - ✔✔Commissioning of
the energy systems



What activity must take place if the Architect determines the project is not substantially complete
after a site inspection? - ✔✔Architect must notify the GC of the remaining work




What action may the Owner take upon the acceptance of substantial completion by the parties? -
✔✔Owner may move in or utilize the work for its intended purpose




For a large, complex building project, who usually hires the commissioning agent? - ✔✔Owner




What is the next activity after the GC has completed the punch list? - ✔✔Architect makes
an inspection to verify substantial completion

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Examsplug. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $13.24. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79373 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$13.24
  • (0)
  Add to cart