100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
NERC Practice Text Questions And Answers 100% Verified. $12.49   Add to cart

Exam (elaborations)

NERC Practice Text Questions And Answers 100% Verified.

 5 views  0 purchase
  • Course
  • NERC
  • Institution
  • NERC

NERC Practice Text Questions And Answers 100% Verified. A transmission line is operating with a voltage phase angle different of 30 degrees between the sending Vs and the receiving bus Vr. If the receiving end load is suddenly increased, the voltage phase angle difference will be? - correct...

[Show more]

Preview 3 out of 19  pages

  • September 16, 2024
  • 19
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
  • NERC
  • NERC
avatar-seller
techgrades
NERC Practice Text Questions And
Answers 100% Verified.

A transmission line is operating with a voltage phase angle different of 30 degrees
between the sending Vs and the receiving bus Vr. If the receiving end load is suddenly
increased, the voltage phase angle difference will be? - correct answer.The phase
angle will increase. When load is increased phase angle will increase.

A load has a power factor of 0.9 lagging. If the load draws 100 MVA, what is the MW
draw? - correct answer.90 pf= mw/mva

The high side of a delta-wye connection transformer is connected to a power system
with 199 kV L-G high side voltage. What is the voltage across the delta winding of the
transformer? - correct answer.Vl-l= square root of 3 times Vl-g 1.73x191= 345kV

If a transmission line is carrying 400 MW and 300 MVAR what is the MVA? - correct
answer.3-4-5 triangle 500 MVA

The prime mover is the component of the generator that creates the rotational force. In
a typical coal fired steam generator what component spins the rotor? - correct
answer.Turbine

Reactive reserve response during a disturbance is best obtained from which devise? -
correct answer.Synchronous condensers

For two identically constructed transmission lines where Line A is 150 miles long and
line B is 15 miles long, if both lines are lightly loaded? - correct answer.A produces
more reactive power than B.

Lightly loaded transmission lines essentially behave like? - correct answer.Shunt
Capacitors

You receive an alarm that indicates low oil pressure on an underground transmission
cable. SCADA shows the pressure is continuing to drop. What is the first step you take
to protect the line? - correct answer.Isolate the line

Computer simulations show that for a 100 MW schedule from Bus A to Bus B, 63% of
the schedule will flow on the scheduled path and the remainder will flow on other
parallel paths. What is the distribution factor for the scheduled path? - correct
answer.63%

,Which statement best describes how reactive power MVAR power normally flows? -
correct answer.High Voltage to Low Voltage

Which of the following types of data are BA and RC not required to share with one
another? - correct answer.Generator start up cost

TOP must develop, maintain, and implement formal policies and procedures to provide
for transmission reliability. Which of the following DOES NOT need to be addressed in
these policies and procedures? - correct answer.Planned outages of generation units

A 1000 MVA rated generator that produces 800 MW and 100 MVAR is best described
as? - correct answer.Operating in a lagging mode. Inductive system

Which of the following types of MW load is the most impacted by an intentional
frequency reduction? - correct answer.Motor

Assume there are two 250 mile long transmission lines exporting an excessive amount
of MW from a generation area to a load area. One of the lines suddenly trips and the
area power system collapses within a few seconds. The most likely cause of the
collapse? - correct answer.Angle Instability

The phase voltage in a wye-connected load is 277 V. What is the line to line voltage? -
correct answer.480 V

A simple power system is composed of three lines connecting generation to load. Each
lines the same impedance, is initially loaded at 200 MW, and has a thermal limit of 400
MW. If one line trips, what the loading on the shortest remaining line be and will the
thermal limit either remaining line be violated? - correct answer.300 MW and No

The best prediction of system load is the load forecast tool that uses? - correct
answer.Forecasted Weather

If the phase angel at an open breaker is equal to 1/10 of a cycle, this is the the same
angle as? - correct answer.1/10 of 360 so 36

A ___________ tool is used to ensure the power system can respond within acceptable
limits of N-1 - correct answer.Contingency Analysis

Which of the following activities would not be included in the procedures for
transmission reliability? - correct answer.Ancillary service pricing

The transmission Operator and BA shall provide documentation that operating
personnel have ______ to implement real time actions to ensure the stable and reliable
operation of the BES. - correct answer.Proper NERC Certification Credential

, A utility distribution bus has the following customer loads attached. What is the total
customer MW load and is the total customer load capacitive or inductive? 5 MW 1
MVAR & 3 MW 1 MVAR & 2 MW -2 MVAR & 10 MW 3 MVAR - correct answer.20 mw
and Inductive

How many MVARs does a 230 kV, 50 MVAR capacitor bank provide when the voltage
id 207 kV - correct answer.Actual MW/ Rated MW ^2 x Capacitor Rating
40

You are a system operator and the load forecast is for an all time summer peak load
day, generations and reactive resources will be tight. Which scheduled job would you
allow to proceed? - correct answer.735 kV shunt reactor maintenance.

A contingency results in the exceedance of an IROL. What could be the result if the
IROL is allowed to be exceeded longer than T sub v - correct answer.Interruption of
power to a large part of the BES

Generators have the ability to be used as voltage control devices. If a generator raises
its VAR output, the system orator should expect system stage to? - correct
answer.Increase

The actual voltage is 362kV on a 345 bus. What is the p.u. voltage? - correct
answer.1.05

In the initial stages of a system restoration condition high transmission system voltage
problems are more likely than low transmission system voltage problems why? - correct
answer.Because of excessive MVAR supply from the energization of transmission lines

All transmission operators shall operate so that instability uncontrolled separation or
cascading outages will not occur in result of? - correct answer.Most severe single
contingency MSSC

A 230kV transmission line is energized at 230kV and is 100 miles long. What is the
approximate line charging contribution? - correct answer.30MVAR

When the system is on the verge of a voltage collapse and nothing else can be done to
alleviate the problem, operating personnel should? - correct answer.Shed Load

The transmission operator shall take corrective actions necessary to prevent voltage
collapse when reactive resources are insufficient including? - correct answer.Shedding
Load

There is a SPS/RAS system out of service for maintenance in your BA. What actions do
you take? - correct answer.Operate within system limits that the SPS/RAS is designed
to protect against

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller techgrades. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for $12.49. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

75619 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
$12.49
  • (0)
  Add to cart