Project Management is defined as:
The discipline of defining and achieving specific goals and objectives for temporary and unique efforts through effective management.
An individual responsible for managing the successful planning, implemen...
CTCM Test A Questions & Answers Solved 100%
Correct!!
Project Management is defined as:
The discipline of defining and achieving specific goals and objectives for temporary and
unique efforts through effective management.
An individual responsible for managing the successful planning, implementation,
and execution of a system, service or product to meet a need while balancing
cost, schedule and performance requirements is a:
Project Manager
One of the four major reasons that projects fail is:
Communications Breakdown
Which of the following is the first step in project initiation?
Define Needs
Documenting and tracking assumptions to resolution is important in order to:
Manage Risk
The scope statement justifies the project by documenting the project objectives,
requirements and deliverables. It becomes the basis for the:
Statement of Work
What are two types of project deliverables?
Internal and External
Which is a project manager's responsibility?
Resist pressure by sponsor or customer to dictate a schedule.
Budget planning involves three processes:
Estimating, Costing, and Pricing
Which technique of cost estimation is a mathematical model based on project
characteristics and historical experience?
Parametric
Which of the following would likely not be a stakeholder in a project to construct
a new highway from Lubbock to Dallas?
A governor from Montana.
In a quality system framework, the highest quality process maturity level is:
Optimizing
Risk management is the estimation and mitigation of which two values?
Risk event probability x risk event impact.
The four risk response methods are:
Avoidance, Transference, Mitigation, Acceptance
The four stages of team development are:
- Forming
- Storming
- Norming
- Performing
Contract management can be defined as:
The entire contracting process from planning through contract administration.
1The four components of contract management framework (CMF) are:
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller LectDan. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $9.69. You're not tied to anything after your purchase.