BSOP 429 Week 8 Final Exam (Version 1) Questions With Best Explained (VERIFIED) With 100% Answers Graded A
(TCO 4) The priority rule, which will sequence jobs in the order they are received, is _____. (TCO 2) In an assignment method problem, if it takes Ab...
bsop 429 week 8 final exam version 1 questions with best explained verified with 100 answers graded a
Written for
BSOP 429
All documents for this subject (3)
Seller
Follow
HIGHSCORE
Reviews received
Content preview
Top of Form
BSOP 429 Week 8 Final Exam
Page 1
1. (TCO 4) The priority rule, which will sequence jobs in the order they are received, is _____. (Points
: 5)
EDD
LIFO
SPT
CR
FCFS
2. (TCO 2) In an assignment method problem, if it takes Abe 3 hours to build a birdhouse & 4 hours
for a doghouse, & Betty takes 4 hours for a birdhouse & 3 hours for a doghouse, what is the reduced
cost (in hours) of assigning Betty to build the doghouse? (Points : 5)
0 hours
1 hour
2 hours
3 hours
4 hours
3. (TCO 2) A major difference between manufacturing & service systems in terms of scheduling is
(Points : 5)
variability in arrival & service rates.
processing cost per unit.
the number of units to be processed.
length of processing time.
output rate.
4. (TCO 3) Scheduling in service systems may involve scheduling which of the following?
(Points : 5)
The workforce
The equipment
A&B
, Customers
All of the above
5. (TCO 5) The owner & operator of the local franchise of Handyman, Inc., has four jobs to do today,
shown in the order they were received:
Job Processing Time (hrs) Due (hrs from now)
-------------------------------------------------------------------------------------------------
W44
X35
Y22
Z11
If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the
average job tardiness? (Points : 5)
0 hours
1.5 hours
1.75 hours
2 hours
2.25 hours
6. (TCO 6) Building up an inventory of standard parts or modules instead of immediately producing
the finished end tems is the essence of (Points : 5)
delayed differentiation.
kanban. autonomation.
andon. matrix management.
7. (TCO 7) With regard to suppliers, JIT systems typically require (Points : 5)
delivery of large lots at regular intervals.
buyer ispection of goods & materials.
multiple sources from which to purchase.
long-trm relationships & commitments.
the lowest price possible.
8. (TCO 1) Which of the following is characteristic of the JIT philosophy? (Points : 5)
Inventries are an asset.
Lot sizes are optimized by formula.
Vendrs are co-workers, essentially other departments of our organization.
Queus are a necessary investment.
All of the above
9. (TCO 1) In make-to-stock systems, fluctuations in sales volume are managed through which of the
following? (Points : 5)
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller HIGHSCORE. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for $15.49. You're not tied to anything after your purchase.